ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
---|---|---|---|---|---|---|
OR0807 #04 Y:2025 | 04 | 2025 | Replace hydraulic / pneumatic equipment with electric equipment | $3,635 | $16,079 |
n/a
|
OR0807 #03 Y:2025 | 03 | 2025 | Reduce the pressure of compressed air to the minimum required | $753 | $2,323 |
n/a
|
OR0807 #02 Y:2025 | 02 | 2025 | Use adjustable frequency drive or multiple speed motors on existing system | $2,721 | $7,534 |
n/a
|
OR0807 #01 Y:2025 | 01 | 2025 | Utilize higher efficiency lamps and/or ballasts | $8,168 | $10,530 |
n/a
|
WM0225 #05 Y:2024 | 05 | 2024 | Utilize energy-efficient belts and other improved mechanisms | $1,246 | $1,375 | |
WM0225 #04 Y:2024 | 04 | 2024 | Recharge batteries on during off-peak demand periods | $3,687 | $4,037 | |
WM0225 #03 Y:2024 | 03 | 2024 | Install compressor air intakes in coolest locations | $6,067 | $5,244 | |
WM0225 #02 Y:2024 | 02 | 2024 | Reduce the pressure of compressed air to the minimum required | $25,176 | - | |
WM0225 #01 Y:2024 | 01 | 2024 | Preheat combustion air with waste heat | $43,885 | $200,000 | |
UD1089 #06 Y:2024 | 06 | 2024 | Use waste heat from hot flue gases to preheat | $6,228 | $27,650 | |
UD1089 #05 Y:2024 | 05 | 2024 | Install occupancy sensors | $472 | $550 | |
UD1089 #04 Y:2024 | 04 | 2024 | Install compressor air intakes in coolest locations | $7,169 | $2,030 | |
UD1089 #03 Y:2024 | 03 | 2024 | Eliminate leaks in inert gas and compressed air lines/ valves | $8,974 | - | |
UD1089 #02 Y:2024 | 02 | 2024 | Utilize energy-efficient belts and other improved mechanisms | $30,384 | - | |
UD1089 #01 Y:2024 | 01 | 2024 | Reschedule plant operations or reduce load to avoid peaks | $79,860 | - | |
KS2208 #06 Y:2022 | 06 | 2022 | Utilize energy-efficient belts and other improved mechanisms | $1,594 | $1,080 | |
KS2208 #05 Y:2022 | 05 | 2022 | Use photocell controls | $1,794 | $2,200 | |
KS2208 #04 Y:2022 | 04 | 2022 | Install occupancy sensors | $5,357 | $5,080 | |
KS2208 #03 Y:2022 | 03 | 2022 | Utilize higher efficiency lamps and/or ballasts | $6,485 | $7,453 | |
KS2208 #02 Y:2022 | 02 | 2022 | Eliminate leaks in inert gas and compressed air lines/ valves | $24,950 | $5,960 |