Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

71

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Paints, varnishes, lacquers, enamels, and allied products
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
BD0423 #12 Y:2013 Regenerate cleaning solvent on-site and reuse $44,983 $302,000
BD0423 #11 Y:2013 Install / repair insulation on steam lines $173 $250
BD0423 #10 Y:2013 Install turbulators $543 $115
BD0423 #09 Y:2013 Recover waste heat from equipment $975 $1,500
BD0423 #08 Y:2013 Use waste heat from hot flue gases to preheat $838 $3,250
BD0423 #07 Y:2013 Install vinyl strip / high speed / air curtain doors $3,404 $2,000
BD0423 #06 Y:2013 Install occupancy sensors $3,795 $9,000
BD0423 #05 Y:2013 Reduce the pressure of compressed air to the minimum required $1,616 $20
BD0423 #04 Y:2013 Utilize higher efficiency lamps and/or ballasts $4,565 $4,565
BD0423 #03 Y:2013 Use / purchase optimum sized compressor $6,135 $100,000
BD0423 #02 Y:2013 Utilize higher efficiency lamps and/or ballasts $12,499 $18,273
BD0423 #01 Y:2013 Install compressor air intakes in coolest locations $26,430 $2,000
BD0363 #11 Y:2009 Minimize water usage $361 $250
BD0363 #10 Y:2009 Minimize water usage $126 $954
BD0363 #09 Y:2009 Insulate glazing, walls, ceilings, and roofs $271 $760
BD0363 #08 Y:2009 Use radiant heater for spot heating $22,508 $28,000
BD0363 #07 Y:2009 Replace obsolete burners with more efficient ones $17,662 $3,500
BD0363 #06 Y:2009 Use most efficient type of electric motors $4,398 $7,180
BD0363 #05 Y:2009 Eliminate leaks in inert gas and compressed air lines/ valves $1,364 $200
BD0363 #04 Y:2009 Reduce the pressure of compressed air to the minimum required $1,380 -