Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

866

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Industrial inorganic chemicals, not elsewhere classified
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
OR0830 #03 Y:2026 Use solar heat to make electricty $70,737 $992,750
OR0830 #02 Y:2026 Utilize controls to operate equipment only when needed $41,804 $330,355
OR0830 #01 Y:2026 Install timers on light switches in little used areas $8,099 $3,940
SU0604 #09 Y:2026 Conserve energy by efficient use of vending machines $47 $341
SU0604 #08 Y:2026 Use adjustable frequency drive or multiple speed motors on existing system $3,371 $19,740
SU0604 #07 Y:2026 Replace fossil fuel equipment with electrical equipment $7,137 $24,539
SU0604 #06 Y:2026 Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings $587 $1,742
SU0604 #05 Y:2026 Insulate bare equipment $745 $2,083
SU0604 #04 Y:2026 Install set-back timers $2,143 $222
SU0604 #03 Y:2026 Reduce the pressure of compressed air to the minimum required $75 -
SU0604 #02 Y:2026 Eliminate/reduce an operation $659 -
SU0604 #01 Y:2026 Reschedule plant operations or reduce load to avoid peaks $13,321 -
GT1000 #08 Y:2025 Optimize plant power factor $1,783 $8,009
GT1000 #07 Y:2025 Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat $228,801 $603,750
GT1000 #06 Y:2025 Install / repair insulation on steam lines $1,088 $2,460
GT1000 #05 Y:2025 Use adjustable frequency drive or multiple speed motors on existing system $5,128 $6,214
GT1000 #04 Y:2025 Adopt in-house material generation $88,408 $75,000
GT1000 #03 Y:2025 Eliminate leaks in inert gas and compressed air lines/ valves $2,557 $1,850
GT1000 #02 Y:2025 Reduce the pressure of compressed air to the minimum required $3,312 $200
GT1000 #01 Y:2025 Apply for tax-free status for energy purchases $55,610 $400