Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

23

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Commercial printing, gravure
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
OK0920 #13 Y:2015 Turn off equipment when not in use $487 $476
OK0920 #12 Y:2015 Change rate schedules or other changes in utility service $20,000 $65,000
OK0920 #11 Y:2015 Optimize plant power factor $3,157 $20,000
OK0920 #10 Y:2015 Eliminate leaks in inert gas and compressed air lines/ valves $3,980 $1,500
OK0920 #09 Y:2015 Use cooling tower or economizer to replace chiller cooling $15,138 $18,243
OK0920 #08 Y:2015 Clean and maintain refrigerant condensers and towers $1,051 -
OK0920 #07 Y:2015 Utilize higher efficiency lamps and/or ballasts $2,921 $2,360
OK0920 #06 Y:2015 Utilize higher efficiency lamps and/or ballasts $1,190 $5,218
OK0920 #05 Y:2015 Utilize higher efficiency lamps and/or ballasts $3,796 $15,971
OK0920 #04 Y:2015 Install partitions to reduce size of conditioned space $820 $3,450
OK0920 #03 Y:2015 Install set-back timers $2,270 $1,550
OK0920 #02 Y:2015 Clean and maintain refrigerant condensers and towers $2,194 -
OK0920 #01 Y:2015 Install outside air damper / economizer on hvac unit $11,299 $3,815
OK0750 #10 Y:2007 Replace existing equipment with more suitable substitutes $4,150,588 $195,000
OK0750 #09 Y:2007 Reduce the pressure of compressed air to the minimum required $1,287 $6,522
OK0750 #08 Y:2007 Eliminate leaks in inert gas and compressed air lines/ valves $2,525 $1,000
OK0750 #07 Y:2007 Utilize higher efficiency lamps and/or ballasts $3,081 $5,998
OK0750 #06 Y:2007 Utilize higher efficiency lamps and/or ballasts $3,311 $7,391
OK0750 #05 Y:2007 Install skylights $5,428 $33,634
OK0750 #04 Y:2007 Shut off cooling if cold outside air will cool process $8,272 $16,000