Assessment Year | 2007 |
---|---|
Principal Product | Commercial printing |
NAICS | 323111: Commercial Printing (except Screen and Books) |
SIC | 2754: Commercial Printing, Gravure |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
90,000
ft2
|
Annual Production | 50,000,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $162,724 | 2,320,800 |
kWh
|
$0.070 |
Electricity Fees | $4,810 | - |
|
- |
Natural Gas | $91,591 | 11,879 |
MMBtu
|
$7.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $4,183,678 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $6,319 | $1,100 |
$6,319
90,277
kWh
|
- | - | |
02 | 2.7211: Clean and maintain refrigerant condensers and towers | $1,776 | $8,988 |
$1,776
25,371
kWh
|
- | - | |
03 | 2.7496: Install partitions to reduce size of conditioned space | $1,091 | $4,248 |
$1,091
15,586
kWh
|
- | - | |
04 | 2.2691: Shut off cooling if cold outside air will cool process | $8,272 | $16,000 |
$8,272
118,171
kWh
|
- | - | |
05 | 2.7145: Install skylights | $5,428 | $33,634 |
$5,428
77,543
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,311 | $7,391 |
$3,311
58,254
kWh
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,081 | $5,998 |
$3,081
44,010
kWh
|
- | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,525 | $1,000 |
$2,525
68,220
kWh
|
- | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,287 | $6,522 |
$1,287
18,380
kWh
|
- | - | |
10 | 4.652: Replace existing equipment with more suitable substitutes | $4,150,588 | $195,000 |
$(-167,327.0)
(-2,390,387)
kWh
|
$62,775
-
MMBtu
|
$4,255,140 | |
TOTAL RECOMMENDED | $4,183,678 | $279,881 |
$(-134,237.0)
(-1,874,575)
kWh
|
$62,775
-
MMBtu
|
$4,255,140 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs