ITAC Assessment: OK0750
ITAC logo
ITAC Assessment: OK0750
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Commercial printing
NAICS 323111: Commercial Printing (except Screen and Books)
SIC 2754: Commercial Printing, Gravure
Sales Range $10
M
to 50
M
# of Employees 75
Plant Area 90,000
ft2
Annual Production 50,000,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $162,724 2,320,800
kWh
Electricity Fees $4,810 -
Natural Gas $91,591 11,879
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,183,678 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Increase in Production Savings
01 2.7261: Install timers and/or thermostats $6,319 $1,100 $6,319
90,277
kWh
- -
02 2.7211: Clean and maintain refrigerant condensers and towers $1,776 $8,988 $1,776
25,371
kWh
- -
03 2.7496: Install partitions to reduce size of conditioned space $1,091 $4,248 $1,091
15,586
kWh
- -
04 2.2691: Shut off cooling if cold outside air will cool process $8,272 $16,000 $8,272
118,171
kWh
- -
05 2.7145: Install skylights $5,428 $33,634 $5,428
77,543
kWh
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $3,311 $7,391 $3,311
58,254
kWh
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $3,081 $5,998 $3,081
44,010
kWh
- -
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,525 $1,000 $2,525
68,220
kWh
- -
09 2.4231: Reduce the pressure of compressed air to the minimum required $1,287 $6,522 $1,287
18,380
kWh
- -
10 4.652: Replace existing equipment with more suitable substitutes $4,150,588 $195,000 $(-167,327.0)
(-2,390,387)
kWh
$62,775
-
MMBtu
$4,255,140
TOTAL RECOMMENDED $4,183,678 $279,881 $(-134,237.0)
(-1,874,575)
kWh
$62,775
-
MMBtu
$4,255,140
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs