| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| IP0006 #07 Y:2012 | 07 | 2012 | Use demand controller or load shedder | $36,010 | $171,310 | |
| IP0006 #06 Y:2012 | 06 | 2012 | Reduce illumination to minimum necessary levels | $18,261 | $92,692 | |
| IP0006 #05 Y:2012 | 05 | 2012 | Install compressor air intakes in coolest locations | $490 | $1,156 | |
| IP0006 #04 Y:2012 | 04 | 2012 | Recover waste heat from equipment | $1,847 | $1,416 | |
| IP0006 #03 Y:2012 | 03 | 2012 | Install occupancy sensors | $1,771 | $730 | |
| IP0006 #02 Y:2012 | 02 | 2012 | Reduce the pressure of compressed air to the minimum required | $980 | - | |
| IP0006 #01 Y:2012 | 01 | 2012 | Eliminate leaks in inert gas and compressed air lines/ valves | $2,520 | - | |
| MZ0080 #07 Y:2012 | 07 | 2012 | Analyze flue gas for proper air/fuel ratio | $306 | - | |
| MZ0080 #06 Y:2012 | 06 | 2012 | Turn off equipment during breaks, reduce operating time | $2,548 | $600 | |
| MZ0080 #05 Y:2012 | 05 | 2012 | Reschedule plant operations or reduce load to avoid peaks | $12,554 | - | |
| MZ0080 #04 Y:2012 | 04 | 2012 | Eliminate leaks in inert gas and compressed air lines/ valves | $7,580 | $850 | |
| MZ0080 #03 Y:2012 | 03 | 2012 | Condense operation into one building | $13,624 | - | |
| MZ0080 #02 Y:2012 | 02 | 2012 | Utilize higher efficiency lamps and/or ballasts | $28,028 | $35,700 | |
| MZ0080 #01 Y:2012 | 01 | 2012 | Utilize energy-efficient belts and other improved mechanisms | $10,819 | - |