*See Full Grant Solicitation for full qualification and selection details.

284

matching recommendations
$
$
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Miscellaneous furniture and fixtures
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
MU0076 #11 Y:2025 Install occupancy sensors $176 $647
MU0076 #10 Y:2025 Use or replace with energy efficient substitutes $412 $3,346
MU0076 #09 Y:2025 Eliminate leaks in inert gas and compressed air lines/ valves $440 $230
MU0076 #08 Y:2025 Use or replace with energy efficient substitutes $139 -
MU0076 #07 Y:2025 Insulate bare equipment $1,132 $5,482
MU0076 #06 Y:2025 Utilize higher efficiency lamps and/or ballasts $6,713 -
MU0076 #05 Y:2025 Use adjustable frequency drive or multiple speed motors on existing system $8,912 $14,934
MU0076 #04 Y:2025 Replace fossil fuel equipment with electrical equipment $12,567 $104,536
MU0076 #03 Y:2025 Insulate glazing, walls, ceilings, and roofs $25,377 $56,072
MU0076 #02 Y:2025 Change procedures / equipment / operating conditions $25,719 $59,150
MU0076 #01 Y:2025 Use solar heat to make electricty $33,420 $529,760
SD0670 #09 Y:2025 Utilize higher efficiency lamps and/or ballasts $459 $1,842
SD0670 #08 Y:2025 Use insulation in furnaces to facilitate heating / cooling $669 $511
SD0670 #07 Y:2025 Use adjustable frequency drive or multiple speed motors on existing system $1,896 $9,455
SD0670 #06 Y:2025 Use adjustable frequency drive or multiple speed motors on existing system $2,220 $3,314
SD0670 #05 Y:2025 Reduce the pressure of compressed air to the minimum required $60 -
SD0670 #04 Y:2025 Eliminate leaks in inert gas and compressed air lines/ valves $161 $932
SD0670 #03 Y:2025 Install direct acting units in place of compressed air pressure system in safety system $1,711 $6,733
SD0670 #02 Y:2025 Use battery storage for demand control $5,044 $470
SD0670 #01 Y:2025 Use solar heat to make electricty $30,558 $134,423