Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

23

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Household and institutional furniture and kitchen cabinet manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
DL0054 #16 Y:2010 Use / purchase optimum sized compressor $950 $900
DL0054 #15 Y:2010 Improve air circulation with destratification fans / other methods $9,900 $36,600
DL0054 #14 Y:2010 Turn off equipment when not in use $3,800 $100
DL0054 #13 Y:2010 Install compressor air intakes in coolest locations $6,000 $2,500
DL0054 #12 Y:2010 Eliminate or reduce compressed air usage $13,100 $8,000
DL0054 #11 Y:2010 Upgrade controls on compressors $25,600 $45,000
DL0054 #10 Y:2010 Replace existing hvac unit with high efficiency model $3,620 $2,400
DL0054 #09 Y:2010 Recover waste heat from equipment $7,800 $3,100
DL0054 #08 Y:2010 Use or replace with energy efficient substitutes $2,100 $3,600
DL0054 #07 Y:2010 Turn off equipment when not in use $2,920 $50
DL0054 #06 Y:2010 Re-use or recycle hot or cold process exhaust air $11,071 $19,300
DL0054 #05 Y:2010 Eliminate leaks in inert gas and compressed air lines/ valves $14,300 $8,000
DL0054 #04 Y:2010 Turn off equipment when not in use $9,200 $1,000
DL0054 #03 Y:2010 Use optimum temperature $20,574 $1
DL0054 #02 Y:2010 Insulate bare equipment $14,240 $2,378
DL0054 #01 Y:2010 Recharge batteries on during off-peak demand periods $15,225 $50
LE0206 #07 Y:2004 Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $63,361 $382,500
LE0206 #06 Y:2004 Eliminate leaks in inert gas and compressed air lines/ valves $683 $200
LE0206 #05 Y:2004 Utilize controls to operate equipment only when needed $3,894 $2,200
LE0206 #04 Y:2004 Use waste heat from hot flue gases to preheat $8,905 $2,500