Assessment Year | 2005 |
---|---|
Principal Product | Urethane Foam |
NAICS | 337121: Upholstered Household Furniture Manufacturing |
SIC | 3086: Plastics Foam Products |
Sales Range | $10 M to 50M |
# of Employees | 62 |
Plant Area |
79,000
ft2
|
Annual Production | 1,000,000
thousand feet
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Delaware |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $68,974 | 1,946,484 |
kWh
|
$0.035 |
Electricity Demand | $59,301 | 9,592 |
kW-mo/yr
|
$6.18 |
Natural Gas | $67,343 | 8,211 |
MMBtu
|
$8.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $255,585 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $43,756 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1321: Replace fossil fuel equipment with electrical equipment | $135,669 | $50,000 | - | - | - | $135,669 | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $31,193 | $5,000 | - | - |
$31,193
-
MMBtu
|
- | |
03 | 4.651: Install back-up equipment | $11,880 | $14,100 |
$9,566
273,312
kWh
|
$2,314
-
kW-mo/yr
|
- | - | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $8,905 | $2,500 | - | - |
$8,905
-
MMBtu
|
- | |
05 | 2.6231: Utilize controls to operate equipment only when needed | $3,894 | $2,200 |
$496
14,175
kWh
|
$505
-
kW-mo/yr
|
$2,893
-
MMBtu
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $683 | $200 |
$338
9,669
kWh
|
$345
-
kW-mo/yr
|
- | - | |
07 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $63,361 | $382,500 |
$17,636
503,880
kWh
|
$18,911
-
kW-mo/yr
|
$26,814
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $255,585 | $456,500 |
$28,036
801,036
kWh
|
$22,075
-
kW-mo/yr
|
$69,805
-
MMBtu
|
$135,669 | ||
TOTAL IMPLEMENTED | $43,756 | $19,300 |
$9,904
282,981
kWh
|
$2,659
-
kW-mo/yr
|
$31,193
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs