CL2111 #05 Y:2021 | 05 | 2021 | Eliminate leaks in inert gas and compressed air lines/ valves | $590 | $2,100 |
n/a
|
CL2111 #04 Y:2021 | 04 | 2021 | Install timers and/or thermostats | $3,930 | - |
n/a
|
CL2111 #03 Y:2021 | 03 | 2021 | Reduce the pressure of compressed air to the minimum required | $512 | - |
n/a
|
CL2111 #02 Y:2021 | 02 | 2021 | Install occupancy sensors | $1,957 | $3,255 |
n/a
|
CL2111 #01 Y:2021 | 01 | 2021 | Utilize higher efficiency lamps and/or ballasts | $5,665 | $4,684 |
n/a
|
CL2109 #07 Y:2021 | 07 | 2021 | Reduce the pressure of compressed air to the minimum required | $32,866 | - |
n/a
|
CL2109 #06 Y:2021 | 06 | 2021 | Keep doors and windows shut when not on use | $1,221 | - |
n/a
|
CL2109 #05 Y:2021 | 05 | 2021 | Turn off equipment when not in use | $105 | - |
n/a
|
CL2109 #04 Y:2021 | 04 | 2021 | Reduce the pressure of compressed air to the minimum required | $7,250 | - |
n/a
|
CL2109 #03 Y:2021 | 03 | 2021 | Install timers and/or thermostats | $32,430 | - |
n/a
|
CL2109 #02 Y:2021 | 02 | 2021 | Install occupancy sensors | $2,121 | $3,410 |
n/a
|
CL2109 #01 Y:2021 | 01 | 2021 | Utilize higher efficiency lamps and/or ballasts | $3,610 | - |
n/a
|
LS2007 #09 Y:2020 | 09 | 2020 | Use or replace with energy efficient substitutes | $4,595 | $34,100 | |
LS2007 #08 Y:2020 | 08 | 2020 | Optimize plant power factor | $8,178 | $56,728 | |
LS2007 #07 Y:2020 | 07 | 2020 | Use waste heat from hot flue gases to preheat incoming fluids | $75,962 | $304,000 | |
LS2007 #06 Y:2020 | 06 | 2020 | Utilize energy-efficient belts and other improved mechanisms | $324 | $970 | |
LS2007 #05 Y:2020 | 05 | 2020 | Utilize higher efficiency lamps and/or ballasts | $235,346 | $155,805 | |
LS2007 #04 Y:2020 | 04 | 2020 | Install occupancy sensors | $1,978 | $559 | |
LS2007 #03 Y:2020 | 03 | 2020 | Eliminate leaks in inert gas and compressed air lines/ valves | $5,236 | $1,080 | |
LS2007 #02 Y:2020 | 02 | 2020 | Reschedule plant operations or reduce load to avoid peaks | $67,360 | $13,000 |