Assessment Year | 2024 |
---|---|
Principal Product | freight car and transit rail car steel castings |
NAICS | 336510: Railroad Rolling Stock Manufacturing |
SIC | 3743: Railroad Equipment |
Sales Range | $10 M to 50M |
# of Employees | 448 |
Plant Area |
739,984
ft2
|
Annual Production | 38,056
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Illinois |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,735,548 | 29,468,906 |
kWh
|
$0.059 | |
Electricity Demand | $255,488 | 227,425 |
kW-mo/yr
|
$1.12 | |
Natural Gas | $448,515 | 131,393 |
MMBtu
|
$3.41 | |
Waste Disposal Costs | |||||
Water Usage | $217,603 | 22,290 |
Tgal
|
$9.76 | |
Water Disposal | $89,643 | 21,199 |
Tgal
|
$4.23 | |
TOTAL YEARLY COSTS | $2,746,797 | ||||
RECOMMENDED SAVINGS* | $238,515 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,699 | $540 |
$1,637
27,741
kWh
|
$62
-
kW-mo/yr
|
- | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $11,598 | $720 |
$11,010
186,619
kWh
|
$588
-
kW-mo/yr
|
- | |
03 | 2.4239: Eliminate or reduce compressed air usage | $2,937 | $816 |
$2,937
49,787
kWh
|
- | - | |
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,037 | $2,400 |
$4,853
82,255
kWh
|
$184
-
kW-mo/yr
|
- | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $211,626 | $267,427 |
$211,626
3,586,888
kWh
|
- | - | |
06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $5,618 | $5,088 |
$(-11.0)
(-186)
kWh
|
- |
$5,629
-
MMBtu
|
|
TOTAL RECOMMENDED | $238,515 | $276,991 |
$232,052
3,933,104
kWh
|
$834
-
kW-mo/yr
|
$5,629
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs