Assessment Year | 2019 |
---|---|
Principal Product | Sand, gravel, concrete |
NAICS | 212321: Construction Sand and Gravel Mining |
SIC | 1442: Construction Sand and Gravel |
Sales Range | $5 M to 10M |
# of Employees | 30 |
Plant Area |
577,800
ft2
|
Annual Production | 350,000
ton
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $34,188 | 857,737 |
kWh
|
$0.040 |
Electricity Demand | $54,335 | 8,892 |
kW-mo/yr
|
$6.11 |
Electricity Fees | $38,832 | - |
|
- |
LPG | $16,169 | 984 |
MMBtu
|
$16.43 |
TOTAL YEARLY COSTS | $143,524 | |||
RECOMMENDED SAVINGS* | $34,762 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | LPG Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.321: Optimize production lot sizes and inventories | $15,651 | $5,000 | - | - | - |
$4,087
-
MMBtu
|
- | $4,087 | - | $7,477 | |
02 | 4.426: Modify workload | $13,223 | $18,824 | - | - | - | - | $13,223 | - | - | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,201 | - |
$502
8,178
kWh
|
$1,699
-
kW-mo/yr
|
- | - | - | - | - | - | |
04 | 2.3212: Optimize plant power factor | $2,657 | $9,364 | - | - | $2,657 | - | - | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,030 | $2,058 |
$858
12,233
kWh
|
$246
-
kW-mo/yr
|
- | - | - | $50 | $(-124.0) | - | |
TOTAL RECOMMENDED | $34,762 | $35,246 |
$1,360
20,411
kWh
|
$1,945
-
kW-mo/yr
|
$2,657 |
$4,087
-
MMBtu
|
$13,223 | $4,137 | $(-124.0) | $7,477 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs