ITAC Assessment: OR0730
ITAC logo
ITAC Assessment: OR0730
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Sand, gravel, concrete
NAICS 212321: Construction Sand and Gravel Mining
SIC 1442: Construction Sand and Gravel
Sales Range $5
M
to 10
M
# of Employees 30
Plant Area 577,800
ft2
Annual Production 350,000
ton
Production Hrs. Annual 2,600
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $34,188 857,737
kWh
Electricity Demand $54,335 8,892
kW-mo/yr
Electricity Fees $38,832 -
LPG $16,169 984
MMBtu
TOTAL YEARLY COSTS $143,524
RECOMMENDED SAVINGS* $34,762 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings LPG Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Increase in Production Savings
01 4.321: Optimize production lot sizes and inventories $15,651 $5,000 - - - $4,087
-
MMBtu
- $4,087 - $7,477
02 4.426: Modify workload $13,223 $18,824 - - - - $13,223 - - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,201 - $502
8,178
kWh
$1,699
-
kW-mo/yr
- - - - - -
04 2.3212: Optimize plant power factor $2,657 $9,364 - - $2,657 - - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,030 $2,058 $858
12,233
kWh
$246
-
kW-mo/yr
- - - $50 $(-124.0) -
TOTAL RECOMMENDED $34,762 $35,246 $1,360
20,411
kWh
$1,945
-
kW-mo/yr
$2,657 $4,087
-
MMBtu
$13,223 $4,137 $(-124.0) $7,477
TOTAL IMPLEMENTED - - - - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs