27
matching recommendations| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| OK1176 #04 Y:2026 | 04 | 2026 | Conserve energy by efficient use of vending machines | $1,191 | $800 |
n/a
|
| OK1176 #03 Y:2026 | 03 | 2026 | Use most efficient type of electric motors | $4,510 | $20,540 |
n/a
|
| OK1176 #02 Y:2026 | 02 | 2026 | Install compressor air intakes in coolest locations | $2,269 | $512 |
n/a
|
| OK1176 #01 Y:2026 | 01 | 2026 | Use solar heat to make electricty | $16,721 | $224,640 |
n/a
|
| OK1043 #05 Y:2021 | 05 | 2021 | Conserve energy by efficient use of vending machines | $2,008 | $952 | |
| OK1043 #04 Y:2021 | 04 | 2021 | Eliminate leaks in inert gas and compressed air lines/ valves | $3,397 | $2,946 | |
| OK1043 #03 Y:2021 | 03 | 2021 | Replace existing hvac unit with high efficiency model | $8,309 | $35,400 | |
| OK1043 #02 Y:2021 | 02 | 2021 | Replace existing hvac unit with high efficiency model | $331 | $1,650 | |
| OK1043 #01 Y:2021 | 01 | 2021 | Replace existing chiller with high efficiency model | $2,091 | $8,000 | |
| OK0802 #10 Y:2010 | 10 | 2010 | Combine utility meters | $936 | $175 | |
| OK0802 #09 Y:2010 | 09 | 2010 | Apply for tax-free status for energy purchases | $11,625 | - | |
| OK0802 #08 Y:2010 | 08 | 2010 | Turn off equipment during breaks, reduce operating time | $23,800 | $15,600 | |
| OK0802 #07 Y:2010 | 07 | 2010 | Use demand controller or load shedder | $30,411 | $45,000 | |
| OK0802 #06 Y:2010 | 06 | 2010 | Turn off equipment during breaks, reduce operating time | $10,918 | $2,775 | |
| OK0802 #05 Y:2010 | 05 | 2010 | Repair faulty insulation in furnaces, boilers, etc | $11,414 | $51,875 | |
| OK0802 #04 Y:2010 | 04 | 2010 | Install occupancy sensors | $1,998 | $13,149 | |
| OK0802 #03 Y:2010 | 03 | 2010 | Reduce illumination to minimum necessary levels | $3,477 | $2,599 | |
| OK0802 #02 Y:2010 | 02 | 2010 | Install compressor air intakes in coolest locations | $8,400 | $1,550 | |
| OK0802 #01 Y:2010 | 01 | 2010 | Replace electrically-operated equipment with fossil fuel equipment | $10,017 | $6,215 | |
| MS0367 #01 Y:2010 | 01 | 2010 | Cover open tanks | $79,614 | $15,421 |