Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

1,074

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Other electrical equipment and component manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
IP0206 #06 Y:2024 Use radiant heater for spot heating $1,970 $4,748
IP0206 #05 Y:2024 Install occupancy sensors $1,174 $877
IP0206 #04 Y:2024 Re-use or recycle hot or cold process exhaust air $719 $419
IP0206 #03 Y:2024 Use adjustable frequency drive or multiple speed motors on existing system $31,184 $17,042
IP0206 #02 Y:2024 Install compressor air intakes in coolest locations $4,530 $714
IP0206 #01 Y:2024 Eliminate leaks in inert gas and compressed air lines/ valves $3,948 $83
OK1134 #04 Y:2024 Change method of deionized water production $257,299 $103,000
OK1134 #03 Y:2024 Recharge batteries on during off-peak demand periods $11,172 -
OK1134 #02 Y:2024 Use solar heat to make electricty $100,152 $858,000
OK1134 #01 Y:2024 Install occupancy sensors $262 -
OK1133 #07 Y:2024 Conserve energy by efficient use of vending machines $819 $480
OK1133 #06 Y:2024 Use radiant heater for spot heating $10,095 $25,179
OK1133 #05 Y:2024 Use adjustable frequency drive or multiple speed motors on existing system $10,253 $7,180
OK1133 #04 Y:2024 Install sub-metering equipment $677 $990
OK1133 #03 Y:2024 Optimize plant power factor $5,711 $4,416
OK1133 #02 Y:2024 Use solar heat to make electricty $23,461 $163,800
OK1133 #01 Y:2024 Utilize higher efficiency lamps and/or ballasts $878 $1,370
GT0988 #06 Y:2024 Use solar heat to make electricty $91,923 $962,674
GT0988 #05 Y:2024 Optimize plant power factor $10,998 $47,093
GT0988 #04 Y:2024 Reduce the pressure of compressed air to the minimum required $598 $200