Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,071

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Computer and electronic product manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
UU0287 #10 Y:2025 Turn off equipment when not in use $8,070 $4,800
UU0287 #09 Y:2025 Insulate bare equipment $3,100 $5,260
UU0287 #08 Y:2025 Use adjustable frequency drive or multiple speed motors on existing system $3,100 $5,900
UU0287 #07 Y:2025 Eliminate or reduce compressed air usage $11,700 $11,700
UU0287 #06 Y:2025 Install occupancy sensors $75,500 $160,000
UU0287 #05 Y:2025 Use solar heat to make electricty $32,200 $261,000
UU0287 #04 Y:2025 Use plant owned transformers or lease transformers $7,500 $10,500
UU0287 #03 Y:2025 Change rate schedules or other changes in utility service $16,300 $2,160
UU0287 #02 Y:2025 Use demand controller or load shedder $40,400 $39,000
UU0287 #01 Y:2025 Use battery storage for demand control $54,000 $20,000
OK1161 #05 Y:2025 Redesign process $57,698 $29,595
OK1161 #04 Y:2025 Use proper thickness of insulation on building envelope $3,533 $109,260
OK1161 #03 Y:2025 Use adjustable frequency drive or multiple speed motors on existing system $3,661 $3,410
OK1161 #02 Y:2025 Eliminate leaks in inert gas and compressed air lines/ valves $5,351 $3,460
OK1161 #01 Y:2025 Install occupancy sensors $245 $900
NT0051 #06 Y:2025 Lower temperature during the winter season and vice-versa $586 -
NT0051 #05 Y:2025 Eliminate leaks in inert gas and compressed air lines/ valves $1,986 $5,609
NT0051 #04 Y:2025 Optimize plant power factor $2,603 $6,709
NT0051 #03 Y:2025 Reduce the pressure of compressed air to the minimum required $12,814 -
NT0051 #02 Y:2025 Replace existing hvac unit with high efficiency model $32,918 $193,830