1,077
matching recommendations| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| NT0071 #05 Y:2026 | 05 | 2026 | Recharge batteries on during off-peak demand periods | $4,096 | - |
n/a
|
| NT0071 #04 Y:2026 | 04 | 2026 | Apply for tax-free status for energy purchases | $15,453 | $5,000 |
n/a
|
| NT0071 #03 Y:2026 | 03 | 2026 | Separate and recycle scrap metal to foundry or for sale | $24,272 | $4,000 |
n/a
|
| NT0071 #02 Y:2026 | 02 | 2026 | Install equipment to move product | $34,500 | $32,000 |
n/a
|
| NT0071 #01 Y:2026 | 01 | 2026 | Purchase equipment instead of leasing | $50,195 | $29,800 |
n/a
|
| OK1175 #05 Y:2026 | 05 | 2026 | Conserve energy by efficient use of vending machines | $168 | $248 |
n/a
|
| OK1175 #04 Y:2026 | 04 | 2026 | Clean and maintain refrigerant condensers and towers | $530 | $964 |
n/a
|
| OK1175 #03 Y:2026 | 03 | 2026 | Use computer programs to optimize hvac performance | $3,749 | $19,250 |
n/a
|
| OK1175 #02 Y:2026 | 02 | 2026 | Eliminate leaks in inert gas and compressed air lines/ valves | $1,605 | $277 |
n/a
|
| OK1175 #01 Y:2026 | 01 | 2026 | Use solar heat to make electricty | $9,655 | $117,936 |
n/a
|
| WV0697 #11 Y:2026 | 11 | 2026 | Utilize energy-efficient belts and other improved mechanisms | $786 | $1,442 |
n/a
|
| WV0697 #10 Y:2026 | 10 | 2026 | Reduce the pressure of compressed air to the minimum required | $1,041 | $450 |
n/a
|
| WV0697 #09 Y:2026 | 09 | 2026 | Upgrade controls on compressors | $1,453 | $2,015 |
n/a
|
| WV0697 #08 Y:2026 | 08 | 2026 | Develop a repair/replace policy | $1,821 | $4,975 |
n/a
|
| WV0697 #07 Y:2026 | 07 | 2026 | Install occupancy sensors | $2,152 | $1,620 |
n/a
|
| WV0697 #06 Y:2026 | 06 | 2026 | Install set-back timers | $2,519 | $1,225 |
n/a
|
| WV0697 #05 Y:2026 | 05 | 2026 | Analyze flue gas for proper air/fuel ratio | $3,285 | $1,296 |
n/a
|
| WV0697 #04 Y:2026 | 04 | 2026 | Establish a predictive maintenance program | $2,950 | $3,300 |
n/a
|
| WV0697 #03 Y:2026 | 03 | 2026 | Eliminate leaks in inert gas and compressed air lines/ valves | $3,389 | $625 |
n/a
|
| WV0697 #02 Y:2026 | 02 | 2026 | Reschedule plant operations or reduce load to avoid peaks | $9,066 | $22,250 |
n/a
|