2,429
matching recommendationsID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
---|---|---|---|---|---|---|
OK1158 #06 Y:2025 | 06 | 2025 | Use adjustable frequency drive or multiple speed motors on existing system | $25,121 | $19,503 |
n/a
|
OK1158 #05 Y:2025 | 05 | 2025 | Optimize plant power factor | $2,728 | $10,239 |
n/a
|
OK1158 #04 Y:2025 | 04 | 2025 | Conserve energy by efficient use of vending machines | $715 | $560 |
n/a
|
OK1158 #03 Y:2025 | 03 | 2025 | Use computer programs to optimize hvac performance | $38,968 | $113,400 |
n/a
|
OK1158 #02 Y:2025 | 02 | 2025 | Clean and maintain refrigerant condensers and towers | $22,291 | $11,690 |
n/a
|
OK1158 #01 Y:2025 | 01 | 2025 | Utilize higher efficiency lamps and/or ballasts | $4,824 | $21,492 |
n/a
|
OR0812 #03 Y:2025 | 03 | 2025 | Use solar heat to make electricty | $25,841 | $172,847 |
n/a
|
OR0812 #02 Y:2025 | 02 | 2025 | Use adjustable frequency drive or multiple speed motors on existing system | $1,333 | $510 |
n/a
|
OR0812 #01 Y:2025 | 01 | 2025 | Utilize higher efficiency lamps and/or ballasts | $2,549 | $373 |
n/a
|
UC2511 #09 Y:2025 | 09 | 2025 | Replace fossil fuel equipment with electrical equipment | $116,730 | $360,000 |
n/a
|
UC2511 #08 Y:2025 | 08 | 2025 | Utilize controls to operate equipment only when needed | $6,726 | $75 |
n/a
|
UC2511 #07 Y:2025 | 07 | 2025 | Use solar heat to make electricty | $225,469 | $2,423,010 |
n/a
|
UC2511 #06 Y:2025 | 06 | 2025 | Insulate bare equipment | $3,267 | $2,180 |
n/a
|
UC2511 #05 Y:2025 | 05 | 2025 | Recover waste heat from equipment | $22,999 | $8,485 |
n/a
|
UC2511 #04 Y:2025 | 04 | 2025 | Use photocell controls | $6,789 | $14,000 |
n/a
|
UC2511 #03 Y:2025 | 03 | 2025 | Install occupancy sensors | $6,520 | $10,625 |
n/a
|
UC2511 #02 Y:2025 | 02 | 2025 | Install compressor air intakes in coolest locations | $2,290 | $2,200 |
n/a
|
UC2511 #01 Y:2025 | 01 | 2025 | Eliminate leaks in inert gas and compressed air lines/ valves | $7,109 | $1,474 |
n/a
|
MU0070 #14 Y:2025 | 14 | 2025 | Pay bills on time to avoid late fees | $178 | - |
n/a
|
MU0070 #13 Y:2025 | 13 | 2025 | Use proper thickness of insulation on building envelope | $61 | $152 |
n/a
|