matching recommendations| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| WM0261 #04 Y:2026 | 04 | 2026 | Eliminate or reduce compressed air usage | $1,552 | $1,075 |
n/a
|
| WM0261 #03 Y:2026 | 03 | 2026 | Reduce space conditioning during non-working hours | $1,994 | $2,950 |
n/a
|
| WM0261 #02 Y:2026 | 02 | 2026 | Install occupancy sensors | $5,340 | $7,400 |
n/a
|
| WM0261 #01 Y:2026 | 01 | 2026 | Utilize higher efficiency lamps and/or ballasts | $8,535 | $5,782 |
n/a
|
| LS2316 #06 Y:2023 | 06 | 2023 | Install occupancy sensors | $460 | $753 | |
| LS2316 #05 Y:2023 | 05 | 2023 | Use adjustable frequency drive or multiple speed motors on existing system | $47,296 | $25,200 | |
| LS2316 #04 Y:2023 | 04 | 2023 | Use photocell controls | $1,069 | $370 | |
| LS2316 #03 Y:2023 | 03 | 2023 | Utilize higher efficiency lamps and/or ballasts | $33,726 | $4,515 | |
| LS2316 #02 Y:2023 | 02 | 2023 | Eliminate leaks in inert gas and compressed air lines/ valves | $1,894 | $135 | |
| LS2316 #01 Y:2023 | 01 | 2023 | Install timers and/or thermostats | $3,030 | $30 | |
| TT0300 #11 Y:2023 | 11 | 2023 | Eliminate leaks in inert gas and compressed air lines/ valves | $1,868 | $1,965 | |
| TT0300 #10 Y:2023 | 10 | 2023 | Upgrade controls on compressors | $8,509 | $17,500 | |
| TT0300 #09 Y:2023 | 09 | 2023 | Reduce the pressure of compressed air to the minimum required | $8,809 | $156 | |
| TT0300 #08 Y:2023 | 08 | 2023 | Utilize higher efficiency lamps and/or ballasts | $10,614 | $19,910 | |
| TT0300 #07 Y:2023 | 07 | 2023 | Use adjustable frequency drive or multiple speed motors on existing system | $12,049 | $13,500 | |
| TT0300 #06 Y:2023 | 06 | 2023 | Use adjustable frequency drive or multiple speed motors on existing system | $14,078 | $18,500 | |
| TT0300 #05 Y:2023 | 05 | 2023 | Recover waste heat from equipment | $18,281 | $13,000 | |
| TT0300 #04 Y:2023 | 04 | 2023 | Use adjustable frequency drive or multiple speed motors on existing system | $20,075 | $30,000 | |
| TT0300 #03 Y:2023 | 03 | 2023 | Optimize plant power factor | $22,385 | $37,500 | |
| TT0300 #02 Y:2023 | 02 | 2023 | Begin a practice of predictive / preventative maintenance | $41,095 | $32,000 |