1,161
matching recommendations| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| NL0143 #07 Y:2026 | 07 | 2026 | Eliminate leaks in inert gas and compressed air lines/ valves | $891 | $500 |
n/a
|
| NL0143 #06 Y:2026 | 06 | 2026 | Install vinyl strip / high speed / air curtain doors | $8,763 | $9,469 |
n/a
|
| NL0143 #05 Y:2026 | 05 | 2026 | Use proper thickness of insulation on building envelope | $19,548 | $85,770 |
n/a
|
| NL0143 #04 Y:2026 | 04 | 2026 | Use proper thickness of insulation on building envelope | $38,419 | $169,049 |
n/a
|
| NL0143 #03 Y:2026 | 03 | 2026 | Consider use / purchase of bulk materials where possible | $90,400 | $300,708 |
n/a
|
| NL0143 #02 Y:2026 | 02 | 2026 | Install adequate dryers on air lines to eliminate blowdown | $104,880 | $43,894 |
n/a
|
| NL0143 #01 Y:2026 | 01 | 2026 | Upgrade obsolete equipment | $431,484 | $274,750 |
n/a
|
| LE0617 #09 Y:2026 | 09 | 2026 | Utilize controls to operate equipment only when needed | $33,706 | $141,920 |
n/a
|
| LE0617 #08 Y:2026 | 08 | 2026 | Remove or close off unneeded compressed air lines | $61,820 | $250,000 |
n/a
|
| LE0617 #07 Y:2026 | 07 | 2026 | Use adjustable frequency drive or multiple speed motors on existing system | $9,955 | $23,000 |
n/a
|
| LE0617 #06 Y:2026 | 06 | 2026 | Install compressor air intakes in coolest locations | $7,300 | $8,000 |
n/a
|
| LE0617 #05 Y:2026 | 05 | 2026 | Re-use or recycle hot or cold process exhaust air | $9,257 | $7,500 |
n/a
|
| LE0617 #04 Y:2026 | 04 | 2026 | Install occupancy sensors | $441 | $296 |
n/a
|
| LE0617 #03 Y:2026 | 03 | 2026 | Eliminate leaks in inert gas and compressed air lines/ valves | $66,793 | $10,440 |
n/a
|
| LE0617 #02 Y:2026 | 02 | 2026 | Reduce the pressure of compressed air to the minimum required | $17,625 | - |
n/a
|
| LE0617 #01 Y:2026 | 01 | 2026 | Eliminate or reduce compressed air usage | $137,524 | - |
n/a
|
| WM0261 #04 Y:2026 | 04 | 2026 | Eliminate or reduce compressed air usage | $1,552 | $1,075 | |
| WM0261 #03 Y:2026 | 03 | 2026 | Reduce space conditioning during non-working hours | $1,994 | $2,950 | |
| WM0261 #02 Y:2026 | 02 | 2026 | Install occupancy sensors | $5,340 | $7,400 | |
| WM0261 #01 Y:2026 | 01 | 2026 | Utilize higher efficiency lamps and/or ballasts | $8,535 | $5,782 |