Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

12,023

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Fabricated metal product manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
AM1009 #07 Y:2026 Upgrade controls on compressors $4,640 $40,001
AM1009 #06 Y:2026 Install an uninteruptable power supply $145,000 $288,927
AM1009 #05 Y:2026 Reduce space conditioning during non-working hours $1,712 $105
AM1009 #04 Y:2026 Reduce the pressure of compressed air to the minimum required $3,183 $30
AM1009 #03 Y:2026 Eliminate leaks in inert gas and compressed air lines/ valves $1,413 $421
AM1009 #02 Y:2026 Combine utility meters $8,665 $25,923
AM1009 #01 Y:2026 Optimize plant power factor $2,830 $2,739
SU0610 #14 Y:2026 Install vinyl strip / high speed / air curtain doors $3,778 $21,942
SU0610 #13 Y:2026 Replace fossil fuel equipment with electrical equipment $10,975 $162,768
SU0610 #12 Y:2026 Use waste heat from hot flue gases to preheat $5,144 $37,640
SU0610 #11 Y:2026 Install occupancy sensors $591 $2,569
SU0610 #10 Y:2026 Install compressor air intakes in coolest locations $200 $830
SU0610 #09 Y:2026 Use or replace with energy efficient substitutes $351 $866
SU0610 #08 Y:2026 Utilize higher efficiency lamps and/or ballasts $9,815 $23,175
SU0610 #07 Y:2026 Install vinyl strip / high speed / air curtain doors $3,372 $3,433
SU0610 #06 Y:2026 Eliminate leaks in inert gas and compressed air lines/ valves $361 $274
SU0610 #05 Y:2026 Reduce the pressure of compressed air to the minimum required $304 -
SU0610 #04 Y:2026 Install set-back timers $532 -
SU0610 #03 Y:2026 Eliminate/reduce an operation $2,983 -
SU0610 #02 Y:2026 Reschedule plant operations or reduce load to avoid peaks $3,976 -