| Assessment Year | 2027 |
|---|---|
| Principal Product | oilfield and industrial hand tools and heavy-duty mechanical components |
| NAICS | 332216: Saw Blade and Handtool Manufacturing |
| SIC | 3423: Hand and Edge Tools, Except Machine Tools and Handsaws |
| Sales Range | $10 M to 50M |
| # of Employees | 58 |
| Plant Area |
88,650
ft2
|
| Annual Production | 612,196
pieces
|
| Production Hrs. Annual | 2,900
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $44,276 | 743,413 |
kWh
|
$0.060 | |
| Electricity Demand | $61,864 | 4,014 |
kW-mo/yr
|
$15.41 | |
| Electricity Fees | $3,551 | - |
|
- | |
| LPG | $2,364 | 48 |
MMBtu
|
$49.25 | |
| Waste Disposal Costs | |||||
| Water Usage | $2,341 | 242 |
Tgal
|
$9.67 | |
| TOTAL YEARLY COSTS | $114,396 | ||||
| RECOMMENDED SAVINGS* | $167,443 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $2,830 | $2,739 | - |
$2,830
-
kW-mo/yr
|
- | - | |
| 02 | 2.8112: Combine utility meters | $8,665 | $25,923 | - |
$6,897
-
kW-mo/yr
|
$1,768 | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,413 | $421 |
$679
11,000
kWh
|
$734
-
kW-mo/yr
|
- | - | |
| 04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,183 | $30 |
$1,160
18,800
kWh
|
$2,023
-
kW-mo/yr
|
- | - | |
| 05 | 2.7224: Reduce space conditioning during non-working hours | $1,712 | $105 |
$1,712
27,750
kWh
|
- | - | - | |
| 06 | 4.631: Install an uninteruptable power supply | $145,000 | $288,927 | - | - | - | $145,000 | |
| 07 | 2.4224: Upgrade controls on compressors | $4,640 | $40,001 |
$1,957
31,718
kWh
|
$2,683
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $167,443 | $358,146 |
$5,508
89,268
kWh
|
$15,167
-
kW-mo/yr
|
$1,768 | $145,000 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs