Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

21

matching recommendations
$
$
ARC 2+ Digits Required
NAICS All other basic organic chemical manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
UD0901 #11 Y:2014 Use adjustable frequency drive or multiple speed motors on existing system $11,379 $16,055
UD0901 #10 Y:2014 Reduce ventilation air $31,388 $33,025
UD0901 #09 Y:2014 Install motor voltage controller on lightly loaded motors $2,267 $8,850
UD0901 #08 Y:2014 Minimize operation of equipment maintained in standby condition $3,748 $1,000
UD0901 #07 Y:2014 Utilize energy-efficient belts and other improved mechanisms $4,426 -
UD0901 #06 Y:2014 Install motor voltage controller on lightly loaded motors $25,546 $28,000
UD0901 #05 Y:2014 Reduce fluid flow rates $151,019 $100,000
UD0901 #04 Y:2014 Recover and reuse cooling water $221,902 $100,000
UD0901 #03 Y:2014 Install occupancy sensors $1,149 $190
UD0901 #02 Y:2014 Make a practice of turning off lights when not needed $4,289 $800
UD0901 #01 Y:2014 Eliminate leaks in inert gas and compressed air lines/ valves $15,645 $1,000
UD0750 #10 Y:2006 Use adjustable frequency drive or multiple speed motors on existing system $7,730 $20,000
UD0750 #09 Y:2006 Repair and eliminate steam leaks $24,000 $13,000
UD0750 #08 Y:2006 Use adjustable frequency drive or multiple speed motors on existing system $39,020 $135,999
UD0750 #07 Y:2006 Use optimum thickness insulation $41,225 $39,892
UD0750 #06 Y:2006 Increase amount of condensate returned $44,000 $25,000
UD0750 #05 Y:2006 Analyze flue gas for proper air/fuel ratio $56,000 -
UD0750 #04 Y:2006 Use most efficient type of electric motors $79,000 $45,000
UD0750 #03 Y:2006 Repair or replace steam traps $155,000 $187,200
UD0750 #02 Y:2006 Use adjustable frequency drive or multiple speed motors on existing system $226,890 $120,000