Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

30

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Cyclic crude, intermediate, and gum and wood chemical manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
UF0501 #09 Y:2016 Utilize higher efficiency lamps and/or ballasts $3,020 $482
UF0501 #08 Y:2016 Utilize daylight whenever possible in lieu of artificial light $5,834 -
UF0501 #07 Y:2016 Use optimum thickness insulation $6,596 $11,216
UF0501 #06 Y:2016 Moderate cooling tower outlet temperature $9,110 $700
UF0501 #05 Y:2016 Use most efficient type of electric motors $29,058 $39,050
UF0501 #04 Y:2016 Repair and eliminate steam leaks $32,236 $1,794
UF0501 #03 Y:2016 Eliminate leaks in inert gas and compressed air lines/ valves $77,438 $2,184
UF0501 #02 Y:2016 Optimize plant power factor $154,176 $60,284
UF0501 #01 Y:2016 Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $1,393,980 $3,306,000
WV0450 #13 Y:2012 Install compressor air intakes in coolest locations $2,764 $1,800
WV0450 #12 Y:2012 Install outside air damper / economizer on hvac unit $7,314 $3,360
WV0450 #11 Y:2012 Develop a repair/replace policy $8,489 $1,210
WV0450 #10 Y:2012 Utilize higher efficiency lamps and/or ballasts $8,953 $18,267
WV0450 #09 Y:2012 Use waste heat from hot flue gases to preheat $9,686 $21,120
WV0450 #08 Y:2012 Establish a predictive maintenance program $10,199 $1,000
WV0450 #07 Y:2012 Install timers on light switches in little used areas $11,389 $6,500
WV0450 #06 Y:2012 Use adjustable frequency drive or multiple speed motors on existing system $36,667 $21,800
WV0450 #05 Y:2012 Use waste heat to produce steam to drive a steam turbine-generator $97,121 $400,000
WV0450 #04 Y:2012 Redesign process $102,043 $230,000
WV0450 #03 Y:2012 Use waste heat from hot flue gases to preheat $130,899 $157,320