Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

94

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Fabric mills
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
NC0666 #04 Y:2021 Use heat from boiler blowdown to preheat boiler feed water $4,768 $10,000
NC0666 #03 Y:2021 Reduce the pressure of compressed air to the minimum required $2,259 $50
NC0666 #02 Y:2021 Size electric motors for peak operating efficiency $24,876 $50,000
NC0666 #01 Y:2021 Utilize higher efficiency lamps and/or ballasts $36,200 $51,808
CL2105 #11 Y:2021 Use flow control valves on equipment to optimize water use $982 $3,050
CL2105 #10 Y:2021 Replace treated water with well / surface water $2,591 $600
CL2105 #09 Y:2021 Install waste heat boiler to provide direct power $24,497 $17,450
CL2105 #08 Y:2021 Utilize energy-efficient belts and other improved mechanisms $25,046 $7,102
CL2105 #07 Y:2021 Use optimum temperature $81,375 -
CL2105 #06 Y:2021 Keep doors and windows shut when not on use $63 -
CL2105 #05 Y:2021 Use solar heat to make electricty $567,975 $4,358,847
CL2105 #04 Y:2021 Eliminate leaks in inert gas and compressed air lines/ valves $23,819 $2,100
CL2105 #03 Y:2021 Reschedule plant operations or reduce load to avoid peaks $34,939 $1,120
CL2105 #02 Y:2021 Install occupancy sensors $25,163 $8,200
CL2105 #01 Y:2021 Utilize higher efficiency lamps and/or ballasts $69,993 $55,908
NC0638 #05 Y:2019 Install occupancy sensors $1,065 $1,900
NC0638 #04 Y:2019 Utilize higher efficiency lamps and/or ballasts $544 $2,464
NC0638 #03 Y:2019 Recover heat from exhausted steam, hot air or hot water $6,164 $6,700
NC0638 #02 Y:2019 Install / repair insulation on steam lines $5,807 $3,600
NC0638 #01 Y:2019 Use waste heat from hot flue gases to preheat $18,797 $85,000