| Assessment Year | 2021 |
|---|---|
| Principal Product | Knitted goods |
| NAICS | 313240: Knit Fabric Mills |
| SIC | 2257: Weft Knit Fabric Mills |
| Sales Range | $50 M to 100M |
| # of Employees | 220 |
| Plant Area |
240,000
ft2
|
| Annual Production | 39,000
thousand feet
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $449,000 | 8,589,000 |
kWh
|
$0.052 | |
| Electricity Demand | $292,852 | 22,725 |
kW-mo/yr
|
$12.89 | |
| Natural Gas | $333,057 | 80,714 |
MMBtu
|
$4.13 | |
| Waste Disposal Costs | |||||
| Water Usage | $181,318 | 90,660 |
Tgal
|
$2.00 | |
| TOTAL YEARLY COSTS | $1,256,227 | ||||
| RECOMMENDED SAVINGS* | $68,103 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $36,200 | $51,808 |
$23,578
450,831
kWh
|
$12,622
-
kW-mo/yr
|
- | - | |
| 02 | 2.4131: Size electric motors for peak operating efficiency | $24,876 | $50,000 |
$16,663
318,600
kWh
|
$8,213
-
kW-mo/yr
|
- | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,259 | $50 |
$1,516
28,994
kWh
|
$743
-
kW-mo/yr
|
- | - | |
| 04 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $4,768 | $10,000 | - | - |
$4,581
-
MMBtu
|
$187
-
Tgal
|
|
| TOTAL RECOMMENDED | $68,103 | $111,858 |
$41,757
798,425
kWh
|
$21,578
-
kW-mo/yr
|
$4,581
-
MMBtu
|
$187
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs