Assessment Year | 2012 |
---|---|
Principal Product | Coated Sheet Steel |
NAICS | 331221: Rolled Steel Shape Manufacturing |
SIC | 3316: Cold-Rolled Steel Sheet, Strip, and Bars |
Sales Range | $100 M to 500M |
# of Employees | 150 |
Plant Area |
373,000
ft2
|
Annual Production | 41,000
pieces
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,362,959 | 56,087,080 |
kWh
|
$0.042 |
Electricity Demand | $583,222 | 52,341 |
kW-mo/yr
|
$11.14 |
Electricity Fees | $(-222,973.0) | - |
|
- |
Natural Gas | $1,808,440 | 738,614 |
MMBtu
|
$2.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $234,813 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $26,051 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,512 | $200 |
$3,512
83,420
kWh
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,236 | $2,700 |
$5,977
141,965
kWh
|
$2,259
-
kW-mo/yr
|
- | - | |
03 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $6,156 | $2,000 |
$4,467
106,105
kWh
|
$1,689
-
kW-mo/yr
|
- | - | |
04 | 2.4131: Size electric motors for peak operating efficiency | $5,354 | $2,350 |
$3,372
80,086
kWh
|
$1,982
-
kW-mo/yr
|
- | - | |
05 | 2.2511: Insulate bare equipment | $14,303 | $13,546 | - | - |
$14,303
-
MMBtu
|
- | |
06 | 2.2414: Use waste heat from hot flue gases to preheat | $3,826 | $6,000 | - | - |
$3,826
-
MMBtu
|
- | |
07 | 2.2693: Use waste heat steam for absorption refrigeration | $28,169 | $55,000 |
$18,418
437,478
kWh
|
$9,751
-
kW-mo/yr
|
- | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $14,363 | $31,050 |
$11,100
263,656
kWh
|
$3,263
-
kW-mo/yr
|
- | - | |
09 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $148,802 | $420,000 |
$137,528
3,266,693
kWh
|
$54,608
-
kW-mo/yr
|
- | $(-43,334.0) | |
10 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,092 | $5,992 |
$1,518
36,060
kWh
|
$574
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $234,813 | $538,838 |
$185,892
4,415,463
kWh
|
$74,126
-
kW-mo/yr
|
$18,129
-
MMBtu
|
$(-43,334.0) | ||
TOTAL IMPLEMENTED | $26,051 | $16,446 |
$9,489
225,385
kWh
|
$2,259
-
kW-mo/yr
|
$14,303
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs