Search Recommendations
ITAC logo
Search Recommendations
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

2,350

matching recommendations
$
$
ARC 2+ Digits Required
NAICS Beverage and tobacco product manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products
ID Description Yearly
Savings
Imp
Cost
LE0612 #07 Y:2026 Use solar heat to heat water $192,683 $758,541
LE0612 #06 Y:2026 Eliminate leaks in inert gas and compressed air lines/ valves $53,150 $155,751
LE0612 #05 Y:2026 Use demand controller or load shedder $138,433 $318,698
LE0612 #04 Y:2026 Replace existing chiller with high efficiency model $355,566 $250,000
LE0612 #03 Y:2026 Install compressor air intakes in coolest locations $65,985 $54,000
LE0612 #02 Y:2026 Use demand controller or load shedder $106,148 $20,000
LE0612 #01 Y:2026 Reduce the pressure of compressed air to the minimum required $18,987 -
UL2605 #06 Y:2026 Use outside cold water source as a supply of cooling water $236,979 $474,400
UL2605 #05 Y:2026 Use solar heat to make electricty $26,708 $193,418
UL2605 #04 Y:2026 Increase amount of condensate returned $29,231 $40,600
UL2605 #03 Y:2026 Install / repair insulation on steam lines $5,070 $3,340
UL2605 #02 Y:2026 Recover waste heat from equipment $5,474 $13,000
UL2605 #01 Y:2026 Eliminate leaks in inert gas and compressed air lines/ valves $1,992 $1,155
AS0613 #07 Y:2026 Utilize higher efficiency lamps and/or ballasts $72 $154
AS0613 #06 Y:2026 Install occupancy sensors $314 $220
AS0613 #05 Y:2026 Insulate bare equipment $1,723 $808
AS0613 #04 Y:2026 Re-arrange equipment layout to reduce labor costs $2,160 $680
AS0613 #03 Y:2026 Use solar heat to make electricty $4,425 $27,975
AS0613 #02 Y:2026 Replace boiler $4,953 $7,100
AS0613 #01 Y:2026 Change rate schedules or other changes in utility service $22,713 $13,550