1,490
matching recommendations| ID | # | Year | Description | Yearly Savings |
Implementation
Imp Cost |
Status |
|---|---|---|---|---|---|---|
| SF0621 #05 Y:2024 | 05 | 2024 | Install steam trap | $9,822 | $1,988 | |
| SF0621 #04 Y:2024 | 04 | 2024 | Eliminate leaks in water lines and valves | $7,560 | $700 | |
| SF0621 #03 Y:2024 | 03 | 2024 | Repair or replace steam traps | $6,435 | $478 | |
| SF0621 #02 Y:2024 | 02 | 2024 | Eliminate leaks in inert gas and compressed air lines/ valves | $4,882 | - | |
| SF0621 #01 Y:2024 | 01 | 2024 | Reduce the pressure of compressed air to the minimum required | $12,755 | $300 | |
| SF0619 #12 Y:2024 | 12 | 2024 | Use adjustable frequency drive or multiple speed motors on existing system | $4,993 | $16,268 |
n/a
|
| SF0619 #11 Y:2024 | 11 | 2024 | Purchase new equipment to reduce material use / cost | $52,391 | $160,125 |
n/a
|
| SF0619 #10 Y:2024 | 10 | 2024 | Install occupancy sensors | $292 | $785 |
n/a
|
| SF0619 #09 Y:2024 | 09 | 2024 | Insulate bare equipment | $2,201 | $2,875 |
n/a
|
| SF0619 #08 Y:2024 | 08 | 2024 | Eliminate or reduce compressed air usage | $6,389 | $4,926 |
n/a
|
| SF0619 #07 Y:2024 | 07 | 2024 | Install steam trap | $531,211 | $270,719 |
n/a
|
| SF0619 #06 Y:2024 | 06 | 2024 | Use closed cycle process to minimize waste water production | $90,155 | $37,058 |
n/a
|
| SF0619 #05 Y:2024 | 05 | 2024 | Use minimum steam operating pressure | $7,106 | $2,700 |
n/a
|
| SF0619 #04 Y:2024 | 04 | 2024 | Use flow control valves on equipment to optimize water use | $39,174 | $7,044 |
n/a
|
| SF0619 #03 Y:2024 | 03 | 2024 | Reschedule plant operations or reduce load to avoid peaks | $241 | - |
n/a
|
| SF0619 #02 Y:2024 | 02 | 2024 | Reduce the pressure of compressed air to the minimum required | $5,589 | $220 |
n/a
|
| SF0619 #01 Y:2024 | 01 | 2024 | Repair and eliminate steam leaks | $4,612 | - |
n/a
|
| CI0032 #09 Y:2024 | 09 | 2024 | Use most efficient type of electric motors | $454 | $1,050 | |
| CI0032 #08 Y:2024 | 08 | 2024 | Install occupancy sensors | $1,100 | $2,025 | |
| CI0032 #07 Y:2024 | 07 | 2024 | Recharge batteries on during off-peak demand periods | $1,346 | $100 |