Assessment Year | 2024 |
---|---|
Principal Product | Frozen Fruit Popsicles |
NAICS | 311520: Ice Cream and Frozen Dessert Manufacturing |
SIC | 2024: Ice Cream and Frozen Desserts |
Sales Range | $1 M to 5M |
# of Employees | 12 |
Plant Area |
18,000
ft2
|
Annual Production | 10,000,000
pieces
|
Production Hrs. Annual | 1,950
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $96,045 | 544,231 |
kWh
|
$0.18 |
Electricity Demand | $36,605 | 2,291 |
kW-mo/yr
|
$15.98 |
Electricity Fees | $10,697 | - |
|
- |
Natural Gas | $2,757 | 276 |
MMBtu
|
$9.99 |
TOTAL YEARLY COSTS | $146,104 | |||
RECOMMENDED SAVINGS* | $88,469 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $47,412 | $313,000 |
$42,378
240,100
kWh
|
$5,034
-
kW-mo/yr
|
- | |
02 | 2.2511: Insulate bare equipment | $10,726 | $2,419 |
$10,726
60,772
kWh
|
- | - | |
03 | 2.7447: Install vinyl strip / high speed / air curtain doors | $9,326 | $24,000 |
$5,426
30,743
kWh
|
- | $3,900 | |
04 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $8,168 | $13,563 |
$8,168
46,276
kWh
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,401 | - |
$5,238
29,676
kWh
|
$163
-
kW-mo/yr
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,536 | $22,885 |
$4,101
23,237
kWh
|
$435
-
kW-mo/yr
|
- | |
07 | 2.3132: Recharge batteries on during off-peak demand periods | $1,346 | $100 | - |
$1,346
-
kW-mo/yr
|
- | |
08 | 2.7135: Install occupancy sensors | $1,100 | $2,025 |
$776
4,397
kWh
|
$324
-
kW-mo/yr
|
- | |
09 | 2.4133: Use most efficient type of electric motors | $454 | $1,050 |
$320
1,812
kWh
|
$134
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $88,469 | $379,042 |
$77,133
437,013
kWh
|
$7,436
-
kW-mo/yr
|
$3,900 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs