| Assessment Year | 2025 |
|---|---|
| Principal Product | Scissor Lift and Aerial Lifts |
| NAICS | 333923: Overhead Traveling Crane, Hoist, and Monorail System Manufacturing |
| SIC | 3531: Construction Machinery and Equipment |
| Sales Range | $50 M to 100M |
| # of Employees | 522 |
| Plant Area |
345,000
ft2
|
| Annual Production | 5,000
units
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $212,235 | 3,251,357 |
kWh
|
$0.065 |
| Electricity Demand | $40,283 | 6,186 |
kW-mo/yr
|
$6.51 |
| Electricity Fees | $15,004 | - |
|
- |
| Natural Gas | $47,572 | 9,940 |
MMBtu
|
$4.79 |
| TOTAL YEARLY COSTS | $315,094 | |||
| RECOMMENDED SAVINGS* | $12,827 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $4,707 | $2,420 |
$3,926
60,128
kWh
|
$781
-
kW-mo/yr
|
- | |
| 02 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $3,650 | $1,300 | - | - |
$3,650
-
MMBtu
|
|
| 03 | 2.4224: Upgrade controls on compressors | $1,332 | $985 |
$1,013
15,513
kWh
|
$319
-
kW-mo/yr
|
- | |
| 04 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $1,279 | $3,050 | - | - |
$1,279
-
MMBtu
|
|
| 05 | 2.4239: Eliminate or reduce compressed air usage | $947 | $500 |
$791
12,120
kWh
|
$156
-
kW-mo/yr
|
- | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $703 | $188 |
$586
8,970
kWh
|
$117
-
kW-mo/yr
|
- | |
| 07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $209 | $60 |
$176
2,696
kWh
|
$33
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $12,827 | $8,503 |
$6,492
99,427
kWh
|
$1,406
-
kW-mo/yr
|
$4,929
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs