Assessment Year | 2000 |
---|---|
Principal Product | Beer |
NAICS |
n/a
|
SIC | 2082: Malt Beverages |
Sales Range | $1 M to 5M |
# of Employees | 20 |
Plant Area |
15,000
ft2
|
Annual Production | 15,000
bbl
|
Production Hrs. Annual | 3,000
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $16,082 | 213,951 |
kWh
|
$0.075 |
Electricity Demand | $6,657 | 767 |
kW-mo/yr
|
$8.68 |
Electricity Fees | $896 | - |
|
- |
Natural Gas | $9,934 | 1,509 |
MMBtu
|
$6.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $34,736 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $31,683 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,601 | $3,600 |
$1,083
14,361
kWh
|
$781
-
kW-mo/yr
|
$(-263.0)
-
MMBtu
|
- | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,300 | $3,542 |
$1,146
15,240
kWh
|
$154
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.2136: Install / repair insulation on steam lines | $152 | $384 | - | - |
$152
-
MMBtu
|
- | - | - | |
04 | 3.4114: Replace city water with recycled water via cooling tower | $1,848 | - |
$(-232.0)
(-3,517)
kWh
|
- | - |
$1,495
-
Tgal
|
- |
$585
-
Tgal
|
|
05 | 4.513: Re-arrange equipment layout to reduce labor costs | $29,835 | $4,434 |
$(-113.0)
(-1,465)
kWh
|
$(-52.0)
-
kW-mo/yr
|
- | - | $30,000 | - | |
TOTAL RECOMMENDED | $34,736 | $11,960 |
$1,884
24,619
kWh
|
$883
-
kW-mo/yr
|
$(-111.0)
-
MMBtu
|
$1,495
-
Tgal
|
$30,000 |
$585
-
Tgal
|
||
TOTAL IMPLEMENTED | $31,683 | $4,434 |
$(-345.0)
(-4,982)
kWh
|
$(-52.0)
-
kW-mo/yr
|
- |
$1,495
-
Tgal
|
$30,000 |
$585
-
Tgal
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs