Assessment Year | 2024 |
---|---|
Principal Product | Chemical Repacker Distributor |
NAICS | 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing |
SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 40 |
Plant Area |
367,927
ft2
|
Annual Production | 180,000
units
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $62,692 | 802,048 |
kWh
|
$0.078 |
Electricity Demand | $23,983 | 2,273 |
kW-mo/yr
|
$10.55 |
Electricity Fees | $3,980 | - |
|
- |
Natural Gas | $41,625 | 3,349 |
MMBtu
|
$12.43 |
TOTAL YEARLY COSTS | $132,280 | |||
RECOMMENDED SAVINGS* | $21,153 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,766 | $8,674 |
$6,630
84,781
kWh
|
$4,136
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,374 | $8,262 |
$2,474
31,641
kWh
|
$1,900
-
kW-mo/yr
|
- | |
03 | 2.7232: Replace existing hvac unit with high efficiency model | $3,331 | $12,440 | - | - |
$3,331
-
MMBtu
|
|
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $696 | $1,133 | - | - |
$696
-
MMBtu
|
|
05 | 2.7232: Replace existing hvac unit with high efficiency model | $658 | $3,214 |
$(-93.0)
(-1,186)
kWh
|
$(-32.0)
-
kW-mo/yr
|
$783
-
MMBtu
|
|
06 | 2.4224: Upgrade controls on compressors | $562 | $2,318 |
$319
4,078
kWh
|
$243
-
kW-mo/yr
|
- | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $393 | $122 |
$221
2,824
kWh
|
$172
-
kW-mo/yr
|
- | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $225 | $88 |
$127
1,628
kWh
|
$98
-
kW-mo/yr
|
- | |
09 | 2.2511: Insulate bare equipment | $148 | $482 | - | - |
$148
-
MMBtu
|
|
TOTAL RECOMMENDED | $21,153 | $36,733 |
$9,678
123,766
kWh
|
$6,517
-
kW-mo/yr
|
$4,958
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs