Assessment Year | 2024 |
---|---|
Principal Product | Electroplating |
NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $1 M to 5M |
# of Employees | 22 |
Plant Area |
28,000
ft2
|
Annual Production | 5,200
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $48,194 | 466,871 |
kWh
|
$0.10 |
Electricity Demand | $21,279 | 1,953 |
kW-mo/yr
|
$10.90 |
Electricity Fees | $8,580 | - |
|
- |
Natural Gas | $23,097 | 3,845 |
MMBtu
|
$6.01 |
TOTAL YEARLY COSTS | $101,150 | |||
RECOMMENDED SAVINGS* | $23,116 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,769 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,612 | $15,969 |
$4,127
39,988
kWh
|
$2,485
-
kW-mo/yr
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,983 | $9,744 |
$3,348
32,443
kWh
|
$1,635
-
kW-mo/yr
|
- | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $4,731 | $9,700 | - |
$4,731
-
kW-mo/yr
|
- | |
04 | 2.4322: Use or replace with energy efficient substitutes | $2,626 | $12,165 | - | - |
$2,626
-
MMBtu
|
|
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,184 | $473 |
$737
7,138
kWh
|
$447
-
kW-mo/yr
|
- | |
06 | 2.4224: Upgrade controls on compressors | $1,021 | $3,645 |
$912
8,836
kWh
|
$109
-
kW-mo/yr
|
- | |
07 | 2.4239: Eliminate or reduce compressed air usage | $618 | $2,517 |
$476
4,608
kWh
|
$142
-
kW-mo/yr
|
- | |
08 | 2.4322: Use or replace with energy efficient substitutes | $523 | $314 |
$327
3,166
kWh
|
$196
-
kW-mo/yr
|
- | |
09 | 2.2511: Insulate bare equipment | $367 | $355 | - | - |
$367
-
MMBtu
|
|
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $233 | $140 |
$178
1,721
kWh
|
$55
-
kW-mo/yr
|
- | |
11 | 2.1233: Analyze flue gas for proper air/fuel ratio | $218 | $713 | - | - |
$218
-
MMBtu
|
|
TOTAL RECOMMENDED | $23,116 | $55,735 |
$10,105
97,900
kWh
|
$9,800
-
kW-mo/yr
|
$3,211
-
MMBtu
|
||
TOTAL IMPLEMENTED | $5,769 | $16,677 |
$1,718
16,633
kWh
|
$840
-
kW-mo/yr
|
$3,211
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs