ITAC Assessment: WV0634
ITAC logo
ITAC Assessment: WV0634
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Wastewater Treatment
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $50
M
to 100
M
# of Employees 30
Plant Area 290,000
ft2
Annual Production 3,630,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Maryland

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $262,718 4,299,254
kWh
Electricity Demand $42,388 17,231
kW-mo/yr
Electricity Fees $10,297 -
Fuel Oil #2 $9,200 301
MMBtu
TOTAL YEARLY COSTS $324,603
RECOMMENDED SAVINGS* $69,318 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,235

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Personnel Changes Savings
01 2.5195: Change product design to reduce energy requirements $45,174 $141,500 $42,812
700,694
kWh
$2,362
-
kW-mo/yr
- -
02 2.4322: Use or replace with energy efficient substitutes $12,909 $43,000 $12,235
200,244
kWh
$674
-
kW-mo/yr
- -
03 2.7135: Install occupancy sensors $8,882 $8,985 $8,417
137,764
kWh
$465
-
kW-mo/yr
- -
04 2.4151: Develop a repair/replace policy $1,166 $1,633 $1,247
20,413
kWh
$69
-
kW-mo/yr
- $(-150.0)
05 2.4157: Establish a predictive maintenance program $973 $1,500 $2,217
36,290
kWh
$123
-
kW-mo/yr
- $(-1,367.0)
06 2.1233: Analyze flue gas for proper air/fuel ratio $214 $908 - - $214
-
MMBtu
-
TOTAL RECOMMENDED $69,318 $197,526 $66,928
1,095,405
kWh
$3,693
-
kW-mo/yr
$214
-
MMBtu
$(-1,517.0)
TOTAL IMPLEMENTED $11,235 $13,026 $11,881
194,467
kWh
$657
-
kW-mo/yr
$214
-
MMBtu
$(-1,517.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs