ITAC Assessment: WV0633
ITAC logo
ITAC Assessment: WV0633
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Water
NAICS 221310: Water Supply and Irrigation Systems
SIC 4941: Water Supply
Sales Range $1
M
to 5
M
# of Employees 13
Plant Area 55,000
ft2
Annual Production 1,000,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $101,487 1,564,510
kWh
Electricity Demand $30,394 2,881
kW-mo/yr
Natural Gas $4,725 324
MMBtu
TOTAL YEARLY COSTS $136,606
RECOMMENDED SAVINGS* $44,237 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,877

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings By-product Production Savings
01 2.5195: Change product design to reduce energy requirements $14,598 $23,000 $11,939
183,960
kWh
$2,659
-
kW-mo/yr
- - -
02 2.4322: Use or replace with energy efficient substitutes $13,775 $16,600 $11,264
173,558
kWh
$2,511
-
kW-mo/yr
- - -
03 3.6126: Direct waste gasses to boiler combustion air $4,724 $12,236 - - $4,724
-
MMBtu
- -
04 4.661: Level zero – install control systems for existing equipment $4,626 $4,080 $3,782
58,271
kWh
$844
-
kW-mo/yr
- - -
05 2.7135: Install occupancy sensors $2,533 $1,543 $2,079
32,038
kWh
$454
-
kW-mo/yr
- - -
06 4.661: Level zero – install control systems for existing equipment $1,637 $5,130 $1,637
25,229
kWh
- - - -
07 2.4157: Establish a predictive maintenance program $1,011 $1,500 $1,323
20,388
kWh
$295
-
kW-mo/yr
- $(-607.0) -
08 2.4151: Develop a repair/replace policy $640 $1,280 $573
8,822
kWh
$127
-
kW-mo/yr
- $(-60.0) -
09 2.2511: Insulate bare equipment $447 $1,572 - - $277
-
MMBtu
- $170
10 2.1233: Analyze flue gas for proper air/fuel ratio $246 $878 - - $146
-
MMBtu
- $100
TOTAL RECOMMENDED $44,237 $67,819 $32,597
502,266
kWh
$6,890
-
kW-mo/yr
$5,147
-
MMBtu
$(-667.0) $270
TOTAL IMPLEMENTED $4,877 $6,773 $3,975
61,248
kWh
$876
-
kW-mo/yr
$423
-
MMBtu
$(-667.0) $270
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs