| Assessment Year | 2021 |
|---|---|
| Principal Product | Distilled Spirits |
| NAICS | 312140: Distilleries |
| SIC | 2085: Distilled and Blended Liquors |
| Sales Range | $10 M to 50M |
| # of Employees | 28 |
| Plant Area |
6,766
ft2
|
| Annual Production | 159
Tgal
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | West Virginia |
| View Case Study | |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $29,162 | 746,827 |
kWh
|
$0.039 | |
| Electricity Demand | $36,410 | 2,107 |
kW-mo/yr
|
$17.28 | |
| Electricity Fees | $2,014 | - |
|
- | |
| Natural Gas | $71,556 | 10,194 |
MMBtu
|
$7.02 | |
| LPG | $1,330 | 66 |
MMBtu
|
$20.15 | |
| Waste Disposal Costs | |||||
| Other Liquid (non-haz) | $91,800 | 540,000 |
gal
|
$0.17 | |
| Solid Waste (non-haz) | $24,550 | 54,000 |
lb
|
$0.45 | |
| Gaseous Waste | $15,085 | 2,011,350 |
lb
|
$0.007 | |
| TOTAL YEARLY COSTS | $271,907 | ||||
| RECOMMENDED SAVINGS* | $59,174 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $59,174 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Gaseous Waste Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.3131: Use evaporation to concentrate material | $24,050 | $90,000 | - | - | - |
$91,800
-
gal
|
$(-24,550.0)
-
lb
|
- | $(-43,200.0) | |
| 02 | 3.5311: Recover and reuse waste material | $15,085 | $15,000 | - | - | - | - | - |
$15,085
-
lb
|
- | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $5,944 | $3,000 | - | - |
$5,944
-
MMBtu
|
- | - | - | - | |
| 04 | 2.4145: Install isolation transformer on adjustable frequency drive | $4,392 | $6,660 |
$2,733
70,080
kWh
|
$1,659
-
kW-mo/yr
|
- | - | - | - | - | |
| 05 | 2.2437: Recover waste heat from equipment | $2,885 | $13,900 | - | - |
$2,885
-
MMBtu
|
- | - | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,355 | $1,691 |
$1,128
28,926
kWh
|
$1,227
-
kW-mo/yr
|
- | - | - | - | - | |
| 07 | 2.2442: Preheat combustion air with waste heat | $2,303 | $10,560 |
$(-175.0)
(-4,487)
kWh
|
- |
$2,478
-
MMBtu
|
- | - | - | - | |
| 08 | 2.2511: Insulate bare equipment | $1,509 | $2,170 | - | - |
$1,509
-
MMBtu
|
- | - | - | - | |
| 09 | 2.4224: Upgrade controls on compressors | $514 | $1,425 |
$319
8,181
kWh
|
$195
-
kW-mo/yr
|
- | - | - | - | - | |
| 10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $137 | $530 |
$85
2,178
kWh
|
$52
-
kW-mo/yr
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $59,174 | $144,936 |
$4,090
104,878
kWh
|
$3,133
-
kW-mo/yr
|
$12,816
-
MMBtu
|
$91,800
-
gal
|
$(-24,550.0)
-
lb
|
$15,085
-
lb
|
$(-43,200.0) | ||
| TOTAL IMPLEMENTED | $59,174 | $144,936 |
$4,090
104,878
kWh
|
$3,133
-
kW-mo/yr
|
$12,816
-
MMBtu
|
$91,800
-
gal
|
$(-24,550.0)
-
lb
|
$15,085
-
lb
|
$(-43,200.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Gaseous Waste Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs