| Assessment Year | 2021 |
|---|---|
| Principal Product | Domestic Airport |
| NAICS | 488119: Other Airport Operations |
| SIC | 4581: Airports, Flying Fields, and Airport Terminal Services |
| Sales Range | $1 M to 5M |
| # of Employees | 11 |
| Plant Area |
64,121
ft2
|
| Annual Production | 5,000
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | West Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $34,170 | 747,835 |
kWh
|
$0.046 |
| Electricity Demand | $30,090 | 1,788 |
kW-mo/yr
|
$16.83 |
| Electricity Fees | $1,560 | - |
|
- |
| Natural Gas | $34,489 | 4,818 |
MMBtu
|
$7.16 |
| TOTAL YEARLY COSTS | $100,309 | |||
| RECOMMENDED SAVINGS* | $27,592 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $9,898 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $9,760 | $21,875 |
$5,435
118,932
kWh
|
$4,325
-
kW-mo/yr
|
- | - | |
| 02 | 2.7232: Replace existing hvac unit with high efficiency model | $8,711 | $49,640 |
$5,790
126,689
kWh
|
$2,921
-
kW-mo/yr
|
- | - | |
| 03 | 2.7241: Install outside air damper / economizer on hvac unit | $4,882 | $9,100 |
$3,990
87,314
kWh
|
$892
-
kW-mo/yr
|
- | - | |
| 04 | 2.7229: Air condition only space necessary | $3,261 | $11,061 |
$486
10,640
kWh
|
$421
-
kW-mo/yr
|
$2,354
-
MMBtu
|
- | |
| 05 | 2.7261: Install timers and/or thermostats | $840 | $1,330 | - | - |
$840
-
MMBtu
|
- | |
| 06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $138 | $750 | - | - |
$183
-
MMBtu
|
$(-45.0) | |
| TOTAL RECOMMENDED | $27,592 | $93,756 |
$15,701
343,575
kWh
|
$8,559
-
kW-mo/yr
|
$3,377
-
MMBtu
|
$(-45.0) | ||
| TOTAL IMPLEMENTED | $9,898 | $22,625 |
$5,435
118,932
kWh
|
$4,325
-
kW-mo/yr
|
$183
-
MMBtu
|
$(-45.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs