Assessment Year | 2020 |
---|---|
Principal Product | Chlorinated Dry Bleach |
NAICS | 325180: Other Basic Inorganic Chemical Manufacturing |
SIC | 2812: Alkalies and Chlorine |
Sales Range | $50 M to 100M |
# of Employees | 232 |
Plant Area |
865,000
ft2
|
Annual Production | 51,700,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,282,009 | 38,688,000 |
kWh
|
$0.033 | |
Electricity Demand | $940,893 | 62,717 |
kW-mo/yr
|
$15.00 | |
Electricity Fees | $114,518 | - |
|
- | |
Natural Gas | $611,704 | 206,312 |
MMBtu
|
$2.96 | |
Waste Disposal Costs | |||||
Water Usage | $1,314,394 | 194,544 |
Tgal
|
$6.76 | |
Water Disposal | $181,045 | 194,544 |
Tgal
|
$0.93 | |
TOTAL YEARLY COSTS | $4,444,563 | ||||
RECOMMENDED SAVINGS* | $299,952 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $135,719 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2128: Use steam condensate for hot water supply (non-potable) | $126,151 | $250,000 |
$(-16,552.0)
(-500,059)
kWh
|
- |
$25,524
-
MMBtu
|
$117,179
-
Tgal
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $50,634 | $94,500 |
$30,249
913,871
kWh
|
$20,385
-
kW-mo/yr
|
- | - | - | |
03 | 2.7241: Install outside air damper / economizer on hvac unit | $25,793 | $83,200 |
$20,378
615,656
kWh
|
$5,415
-
kW-mo/yr
|
- | - | - | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $18,379 | $45,860 | - | - |
$18,379
-
MMBtu
|
- | - | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $15,981 | $2,000 | - | - |
$16,461
-
MMBtu
|
- | $(-480.0) | |
06 | 2.4151: Develop a repair/replace policy | $13,389 | $2,433 |
$8,224
248,473
kWh
|
$5,325
-
kW-mo/yr
|
- | - | $(-160.0) | |
07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,054 | $14,700 |
$7,314
220,975
kWh
|
$4,740
-
kW-mo/yr
|
- | - | - | |
08 | 2.1221: Replace obsolete burners with more efficient ones | $10,828 | $39,480 | - | - |
$10,828
-
MMBtu
|
- | - | |
09 | 2.1116: Improve combustion control capability | $9,278 | $8,650 | - | - |
$9,398
-
MMBtu
|
- | $(-120.0) | |
10 | 2.2437: Recover waste heat from equipment | $7,356 | $21,400 | - | - |
$7,356
-
MMBtu
|
- | - | |
11 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $4,587 | $27,500 |
$2,787
84,209
kWh
|
$1,800
-
kW-mo/yr
|
- | - | - | |
12 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,517 | $2,256 |
$2,137
64,565
kWh
|
$1,380
-
kW-mo/yr
|
- | - | - | |
13 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,644 | $1,250 |
$999
30,182
kWh
|
$645
-
kW-mo/yr
|
- | - | - | |
14 | 2.2511: Insulate bare equipment | $361 | $1,123 | - | - |
$361
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $299,952 | $594,352 |
$55,536
1,677,872
kWh
|
$39,690
-
kW-mo/yr
|
$88,307
-
MMBtu
|
$117,179
-
Tgal
|
$(-760.0) | ||
TOTAL IMPLEMENTED | $135,719 | $266,289 |
$61,077
1,845,249
kWh
|
$32,565
-
kW-mo/yr
|
$42,557
-
MMBtu
|
- | $(-480.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs