Assessment Year | 2020 |
---|---|
Principal Product | Manufacturing Custom Metal |
NAICS | 332710: Machine Shops |
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 15 |
Plant Area |
15,000
ft2
|
Annual Production | 400,000
units
|
Production Hrs. Annual | 2,652
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $56,140 | 1,303,830 |
kWh
|
$0.043 |
Electricity Demand | $39,839 | 2,924 |
kW-mo/yr
|
$13.62 |
Natural Gas | $19,301 | 2,499 |
MMBtu
|
$7.72 |
TOTAL YEARLY COSTS | $115,280 | |||
RECOMMENDED SAVINGS* | $14,763 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,848 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $7,138 | $5,700 | - |
$7,138
-
kW-mo/yr
|
- | - | |
02 | 2.4322: Use or replace with energy efficient substitutes | $2,478 | $12,144 |
$1,022
23,708
kWh
|
$1,456
-
kW-mo/yr
|
- | - | |
03 | 2.2511: Insulate bare equipment | $1,313 | $6,099 | - | - |
$1,313
-
MMBtu
|
- | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $1,299 | $4,225 |
$(-83.0)
(-1,928)
kWh
|
- |
$1,382
-
MMBtu
|
- | |
05 | 2.7135: Install occupancy sensors | $1,263 | $3,355 |
$882
20,457
kWh
|
$381
-
kW-mo/yr
|
- | - | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $650 | $1,100 | - | - |
$778
-
MMBtu
|
$(-128.0) | |
07 | 2.4151: Develop a repair/replace policy | $315 | $406 |
$199
4,606
kWh
|
$286
-
kW-mo/yr
|
- | $(-170.0) | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $188 | $305 |
$79
1,840
kWh
|
$109
-
kW-mo/yr
|
- | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $119 | $85 |
$51
1,179
kWh
|
$68
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $14,763 | $33,419 |
$2,150
49,862
kWh
|
$9,438
-
kW-mo/yr
|
$3,473
-
MMBtu
|
$(-298.0) | ||
TOTAL IMPLEMENTED | $3,848 | $11,350 |
$1,211
28,082
kWh
|
$844
-
kW-mo/yr
|
$2,091
-
MMBtu
|
$(-298.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs