Assessment Year | 2002 |
---|---|
Principal Product | Teflon and metal hose products |
NAICS |
n/a
|
SIC | 3052: Rubber and Plastics Hose and Belting |
Sales Range | $100 M to 500M |
# of Employees | 545 |
Plant Area |
250,000
ft2
|
Annual Production | 15,500,000
lb
|
Production Hrs. Annual | 6,552
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $680,219 | 14,199,135 |
kWh
|
$0.048 |
Electricity Demand | $354,580 | 26,202 |
kW-mo/yr
|
$13.53 |
Electricity Fees | $174,113 | - |
|
- |
Natural Gas | $210,373 | 32,079 |
MMBtu
|
$6.56 |
Fuel Oil #2 | $11,794 | 1,496 |
MMBtu
|
$7.88 |
Fuel Oil #4 | $138,878 | 27,933 |
MMBtu
|
$4.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $66,265 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $54,568 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #4 Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2514: Cover open tanks | $30,107 | $4,262 | - |
$30,107
-
MMBtu
|
- | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $11,697 | $33,800 |
$21,174
428,062
kWh
|
- |
$(-9,477.0)
-
MMBtu
|
- | |
03 | 2.2212: Use minimum safe oven ventilation | $7,427 | $2,100 |
$7,095
147,325
kWh
|
- |
$332
-
MMBtu
|
- | |
04 | 4.821: Pay bills on time to avoid late fees | $6,528 | - | - | - | - | $6,528 | |
05 | 2.2511: Insulate bare equipment | $6,349 | $9,636 | - |
$6,349
-
MMBtu
|
- | - | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,140 | $5,200 |
$2,140
43,274
kWh
|
- | - | - | |
07 | 2.4221: Install compressor air intakes in coolest locations | $1,164 | $2,500 |
$1,164
28,151
kWh
|
- | - | - | |
08 | 2.6242: Minimize operation of equipment maintained in standby condition | $853 | $1,515 |
$853
19,691
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $66,265 | $59,013 |
$32,426
666,503
kWh
|
$36,456
-
MMBtu
|
$(-9,145.0)
-
MMBtu
|
$6,528 | ||
TOTAL IMPLEMENTED | $54,568 | $25,213 |
$11,252
238,441
kWh
|
$36,456
-
MMBtu
|
$332
-
MMBtu
|
$6,528 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #4 Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs