| Assessment Year | 2018 |
|---|---|
| Principal Product | Automobile plastic parts |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 1,000 |
| Plant Area |
590,000
ft2
|
| Annual Production | 90,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $3,749,076 | 43,162,347 |
kWh
|
$0.087 | |
| Electricity Demand | $659,585 | 82,448 |
kW-mo/yr
|
$8.00 | |
| Natural Gas | $846,973 | 182,370 |
MMBtu
|
$4.64 | |
| Waste Disposal Costs | |||||
| Water Usage | $2,602 | 788 |
Tgal
|
$3.30 | |
| TOTAL YEARLY COSTS | $5,258,236 | ||||
| RECOMMENDED SAVINGS* | $238,323 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $21,468 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4224: Upgrade controls on compressors | $85,272 | $36,000 |
$85,272
981,280
kWh
|
- | - | - | - | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $83,489 | $54,000 |
$83,489
960,744
kWh
|
- | - | - | - | |
| 03 | 2.2437: Recover waste heat from equipment | $35,888 | $173,323 |
$24,072
277,004
kWh
|
$11,816
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4151: Develop a repair/replace policy | $20,002 | $754 |
$18,114
208,444
kWh
|
$2,288
-
kW-mo/yr
|
- | $(-400.0) | - | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $12,206 | $59,750 |
$12,206
140,458
kWh
|
- | - | - | - | |
| 06 | 3.4151: Minimize water usage | $1,202 | $1,400 | - | - | - | $(-1,400.0) |
$2,602
-
Tgal
|
|
| 07 | 2.2511: Insulate bare equipment | $264 | $235 | - | - |
$264
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $238,323 | $325,462 |
$223,153
2,567,930
kWh
|
$14,104
-
kW-mo/yr
|
$264
-
MMBtu
|
$(-1,800.0) |
$2,602
-
Tgal
|
||
| TOTAL IMPLEMENTED | $21,468 | $2,389 |
$18,114
208,444
kWh
|
$2,288
-
kW-mo/yr
|
$264
-
MMBtu
|
$(-1,800.0) |
$2,602
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs