Assessment Year | 2015 |
---|---|
Principal Product | Coated Steel Sheets |
NAICS | 332431: Metal Can Manufacturing |
SIC | 3411: Metal Cans |
Sales Range | $50 M to 100M |
# of Employees | 63 |
Plant Area |
300,000
ft2
|
Annual Production | 50,000
ton
|
Production Hrs. Annual | 6,912
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $159,385 | 4,649,432 |
kWh
|
$0.034 |
Electricity Demand | $157,292 | 11,964 |
kW-mo/yr
|
$13.15 |
Natural Gas | $653,004 | 121,846 |
MMBtu
|
$5.36 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $251,110 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,211 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $227,708 | $366,480 |
$(-7,457.0)
(-217,404)
kWh
|
$(-4,958.0)
-
kW-mo/yr
|
$240,123
-
MMBtu
|
- | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $8,331 | - |
$5,004
145,877
kWh
|
$3,327
-
kW-mo/yr
|
- | - | |
03 | 2.4157: Establish a predictive maintenance program | $6,021 | $1,000 |
$4,484
130,720
kWh
|
$2,985
-
kW-mo/yr
|
- | $(-1,448.0) | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,146 | $3,449 |
$1,857
54,139
kWh
|
$1,289
-
kW-mo/yr
|
- | - | |
05 | 2.2511: Insulate bare equipment | $2,835 | $885 | - | - |
$2,835
-
MMBtu
|
- | |
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,057 | $4,884 |
$636
18,544
kWh
|
$421
-
kW-mo/yr
|
- | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $860 | $39 |
$518
15,095
kWh
|
$342
-
kW-mo/yr
|
- | - | |
08 | 2.4239: Eliminate or reduce compressed air usage | $599 | $182 |
$362
10,541
kWh
|
$237
-
kW-mo/yr
|
- | - | |
09 | 2.4151: Develop a repair/replace policy | $553 | $634 |
$883
25,737
kWh
|
$592
-
kW-mo/yr
|
- | $(-922.0) | |
TOTAL RECOMMENDED | $251,110 | $377,553 |
$6,287
183,249
kWh
|
$4,235
-
kW-mo/yr
|
$242,958
-
MMBtu
|
$(-2,370.0) | ||
TOTAL IMPLEMENTED | $14,211 | $11,034 |
$8,222
239,681
kWh
|
$5,524
-
kW-mo/yr
|
$2,835
-
MMBtu
|
$(-2,370.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs