Assessment Year | 2013 |
---|---|
Principal Product | printed material |
NAICS | 323111: Commercial Printing (except Screen and Books) |
SIC | 2759: Commercial Printing, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 230 |
Plant Area |
450,000
ft2
|
Annual Production | 55,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,125,265 | 34,080,000 |
kWh
|
$0.062 |
Electricity Demand | $217,349 | 65,293 |
kW-mo/yr
|
$3.33 |
Natural Gas | $1,450,677 | 276,737 |
MMBtu
|
$5.24 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $173,560 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $83,443 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $47,093 | - |
$43,916
703,785
kWh
|
$3,177
-
kW-mo/yr
|
- | - | |
02 | 2.4157: Establish a predictive maintenance program | $32,413 | $1,000 |
$32,098
514,385
kWh
|
$2,348
-
kW-mo/yr
|
- | $(-2,033.0) | |
03 | 2.1221: Replace obsolete burners with more efficient ones | $28,584 | $36,500 | - | - |
$28,584
-
MMBtu
|
- | |
04 | 2.2437: Recover waste heat from equipment | $15,736 | $4,480 | - | - |
$15,736
-
MMBtu
|
- | |
05 | 2.4151: Develop a repair/replace policy | $9,967 | $1,388 |
$9,848
157,823
kWh
|
$719
-
kW-mo/yr
|
- | $(-600.0) | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,444 | $1,100 |
$6,938
111,190
kWh
|
$506
-
kW-mo/yr
|
- | - | |
07 | 2.7135: Install occupancy sensors | $6,892 | $1,275 |
$6,422
102,914
kWh
|
$470
-
kW-mo/yr
|
- | - | |
08 | 2.4239: Eliminate or reduce compressed air usage | $4,928 | $4,833 |
$4,592
73,584
kWh
|
$336
-
kW-mo/yr
|
- | - | |
09 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,776 | $1,700 | - | - |
$4,826
-
MMBtu
|
$(-50.0) | |
10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,736 | $19,676 |
$4,133
66,233
kWh
|
$603
-
kW-mo/yr
|
- | - | |
11 | 2.2113: Repair or replace steam traps | $4,104 | $6,095 | - | - |
$4,187
-
MMBtu
|
$(-83.0) | |
12 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,996 | $595 |
$3,723
59,664
kWh
|
$273
-
kW-mo/yr
|
- | - | |
13 | 2.2136: Install / repair insulation on steam lines | $2,332 | $3,845 | - | - |
$2,332
-
MMBtu
|
- | |
14 | 2.2625: Chill water to the highest temperature possible | $559 | $50 |
$522
8,362
kWh
|
$37
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $173,560 | $82,537 |
$112,192
1,797,940
kWh
|
$8,469
-
kW-mo/yr
|
$55,665
-
MMBtu
|
$(-2,766.0) | ||
TOTAL IMPLEMENTED | $83,443 | $19,828 |
$59,551
954,338
kWh
|
$4,353
-
kW-mo/yr
|
$22,255
-
MMBtu
|
$(-2,716.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs