Assessment Year | 2013 |
---|---|
Principal Product | electronic connectors and cables |
NAICS | 334417: Electronic Connector Manufacturing |
SIC | 3678: Electronic Connectors |
Sales Range | $10 M to 50M |
# of Employees | 230 |
Plant Area |
126,000
ft2
|
Annual Production | 200,000
units
|
Production Hrs. Annual | 2,288
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $102,536 | 1,098,885 |
kWh
|
$0.093 |
Electricity Demand | $36,714 | 4,979 |
kW-mo/yr
|
$7.37 |
Natural Gas | $40,446 | 5,221 |
MMBtu
|
$7.75 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $39,352 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $30,643 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,046 | $26,555 |
$10,801
115,768
kWh
|
$4,245
-
kW-mo/yr
|
- | - | |
02 | 2.7261: Install timers and/or thermostats | $13,346 | $4,200 | - | - |
$13,346
-
MMBtu
|
- | |
03 | 2.8112: Combine utility meters | $3,940 | $1,800 | - | - | - | $3,940 | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,749 | $5,400 | - |
$2,749
-
kW-mo/yr
|
- | - | |
05 | 2.2437: Recover waste heat from equipment | $845 | $1,940 | - | - |
$845
-
MMBtu
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $756 | $3,667 |
$756
8,103
kWh
|
- | - | - | |
07 | 2.7229: Air condition only space necessary | $643 | $3,920 | - | - |
$643
-
MMBtu
|
- | |
08 | 2.4239: Eliminate or reduce compressed air usage | $621 | $233 |
$437
4,689
kWh
|
$184
-
kW-mo/yr
|
- | - | |
09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $595 | $1,431 |
$411
4,404
kWh
|
$184
-
kW-mo/yr
|
- | - | |
10 | 2.4235: Remove or close off unneeded compressed air lines | $301 | $90 |
$213
2,283
kWh
|
$88
-
kW-mo/yr
|
- | - | |
11 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $259 | $140 |
$185
1,980
kWh
|
$74
-
kW-mo/yr
|
- | - | |
12 | 2.4231: Reduce the pressure of compressed air to the minimum required | $251 | $50 |
$177
1,902
kWh
|
$74
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $39,352 | $49,426 |
$12,980
139,129
kWh
|
$7,598
-
kW-mo/yr
|
$14,834
-
MMBtu
|
$3,940 | ||
TOTAL IMPLEMENTED | $30,643 | $34,406 |
$11,787
126,337
kWh
|
$4,665
-
kW-mo/yr
|
$14,191
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs