ITAC Assessment: WV0474
ITAC logo
ITAC Assessment: WV0474
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product automotive ignition coils
NAICS 336320: Motor Vehicle Electrical and Electronic Equipment Manufacturing
SIC 3694: Electrical Equipment for Internal Combustion Engines
Sales Range $100
M
to 500
M
# of Employees 320
Plant Area 110,000
ft2
Annual Production 12,000,000
pieces
Production Hrs. Annual 8,400
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $426,310 11,082,950
kWh
Electricity Demand $251,820 18,442
kW-mo/yr
Electricity Fees $3,374 -
Natural Gas $17,139 2,129
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $40,206 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $25,312

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $12,986 $15,864 $8,618
223,839
kWh
$4,368
-
kW-mo/yr
- -
02 2.4239: Eliminate or reduce compressed air usage $9,866 $21,080 $6,549
170,100
kWh
$3,317
-
kW-mo/yr
- -
03 2.4157: Establish a predictive maintenance program $5,698 $1,000 $6,111
158,739
kWh
$3,099
-
kW-mo/yr
- $(-3,512.0)
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,360 - $2,227
57,842
kWh
$1,133
-
kW-mo/yr
- -
05 2.2625: Chill water to the highest temperature possible $2,920 $72 $1,937
50,319
kWh
$983
-
kW-mo/yr
- -
06 2.4151: Develop a repair/replace policy $1,715 $392 $1,231
31,985
kWh
$628
-
kW-mo/yr
- $(-144.0)
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,586 $324 $1,054
27,384
kWh
$532
-
kW-mo/yr
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $967 $6,150 $489
12,692
kWh
$478
-
kW-mo/yr
- -
09 2.4239: Eliminate or reduce compressed air usage $701 $960 $469
12,180
kWh
$232
-
kW-mo/yr
- -
10 2.1233: Analyze flue gas for proper air/fuel ratio $407 $500 - - $515
-
MMBtu
$(-108.0)
TOTAL RECOMMENDED $40,206 $46,342 $28,685
745,080
kWh
$14,770
-
kW-mo/yr
$515
-
MMBtu
$(-3,764.0)
TOTAL IMPLEMENTED $25,312 $18,152 $18,951
492,266
kWh
$9,610
-
kW-mo/yr
$515
-
MMBtu
$(-3,764.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs