| Assessment Year | 2013 |
|---|---|
| Principal Product | Beer |
| NAICS | 312120: Breweries |
| SIC | 2082: Malt Beverages |
| Sales Range | $50 M to 100M |
| # of Employees | 205 |
| Plant Area |
421,180
ft2
|
| Annual Production | 30,000
Tgal
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $604,930 | 15,862,285 |
kWh
|
$0.038 |
| Electricity Demand | $56,149 | 32,738 |
kW-mo/yr
|
$1.72 |
| Electricity Fees | $5,698 | - |
|
- |
| Natural Gas | $656,768 | 135,876 |
MMBtu
|
$4.83 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $41,732 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $15,525 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,047 | $31,578 |
$14,717
386,278
kWh
|
$1,330
-
kW-mo/yr
|
- | - | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,907 | $8,793 |
$6,334
166,255
kWh
|
$573
-
kW-mo/yr
|
- | - | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,804 | $1,700 | - | - |
$5,023
-
MMBtu
|
$(-219.0) | |
| 04 | 2.4157: Establish a predictive maintenance program | $3,703 | $1,000 |
$6,596
173,118
kWh
|
$595
-
kW-mo/yr
|
- | $(-3,488.0) | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,539 | $7,466 |
$3,247
85,220
kWh
|
$292
-
kW-mo/yr
|
- | - | |
| 06 | 2.2511: Insulate bare equipment | $2,574 | $3,281 | - | - |
$2,574
-
MMBtu
|
- | |
| 07 | 2.7221: Lower temperature during the winter season and vice-versa | $1,724 | $617 | - | - |
$1,724
-
MMBtu
|
- | |
| 08 | 2.7241: Install outside air damper / economizer on hvac unit | $1,529 | $3,263 |
$1,440
37,797
kWh
|
$89
-
kW-mo/yr
|
- | - | |
| 09 | 2.4151: Develop a repair/replace policy | $497 | $566 |
$618
16,230
kWh
|
$55
-
kW-mo/yr
|
- | $(-176.0) | |
| 10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $408 | $29 |
$374
9,811
kWh
|
$34
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $41,732 | $58,293 |
$33,326
874,709
kWh
|
$2,968
-
kW-mo/yr
|
$9,321
-
MMBtu
|
$(-3,883.0) | ||
| TOTAL IMPLEMENTED | $15,525 | $14,042 |
$10,835
284,379
kWh
|
$976
-
kW-mo/yr
|
$7,597
-
MMBtu
|
$(-3,883.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs