ITAC Assessment: WV0451
ITAC logo
ITAC Assessment: WV0451
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Rail Joints
NAICS 336510: Railroad Rolling Stock Manufacturing
SIC 3743: Railroad Equipment
Sales Range $10
M
to 50
M
# of Employees 37
Plant Area 219,000
ft2
Annual Production 30,771
ton
Production Hrs. Annual 4,160
hrs
Location (State) West Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $220,391 3,290,400
kWh
Electricity Demand $59,755 10,824
kW-mo/yr
Natural Gas $67,150 9,011
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $64,977 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,308

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $21,277 $41,953 $17,192
256,671
kWh
$4,085
-
kW-mo/yr
- -
02 2.4156: Establish a preventative maintenance program $6,271 $1,000 $5,216
77,872
kWh
$1,242
-
kW-mo/yr
- $(-187.0)
03 2.7142: Utilize higher efficiency lamps and/or ballasts $5,062 $5,773 $4,090
61,062
kWh
$972
-
kW-mo/yr
- -
04 2.1221: Replace obsolete burners with more efficient ones $4,597 $27,000 - - $4,597
-
MMBtu
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,858 $380 $3,113
46,768
kWh
$745
-
kW-mo/yr
- -
06 2.2511: Insulate bare equipment $3,732 $1,737 $3,014
44,995
kWh
$718
-
kW-mo/yr
- -
07 2.3131: Reschedule plant operations or reduce load to avoid peaks $3,357 $5,400 - $3,357
-
kW-mo/yr
- -
08 2.4231: Reduce the pressure of compressed air to the minimum required $3,273 $10,200 $2,644
39,481
kWh
$629
-
kW-mo/yr
- -
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,705 $9,700 $2,186
32,637
kWh
$519
-
kW-mo/yr
- -
10 2.4151: Develop a repair/replace policy $2,628 $640 $2,898
43,262
kWh
$690
-
kW-mo/yr
- $(-960.0)
11 2.2414: Use waste heat from hot flue gases to preheat $1,982 $9,000 - - $1,982
-
MMBtu
-
12 2.4221: Install compressor air intakes in coolest locations $1,612 $1,260 $1,303
19,459
kWh
$309
-
kW-mo/yr
- -
13 2.1233: Analyze flue gas for proper air/fuel ratio $1,600 $2,500 - - $1,900
-
MMBtu
$(-300.0)
14 2.7142: Utilize higher efficiency lamps and/or ballasts $1,239 $5,054 $952
14,218
kWh
$287
-
kW-mo/yr
- -
15 2.4239: Eliminate or reduce compressed air usage $1,001 $467 $1,001
14,944
kWh
- - -
16 2.4235: Remove or close off unneeded compressed air lines $783 $70 $783
11,692
kWh
- - -
TOTAL RECOMMENDED $64,977 $122,134 $44,392
663,061
kWh
$13,553
-
kW-mo/yr
$8,479
-
MMBtu
$(-1,447.0)
TOTAL IMPLEMENTED $18,308 $20,660 $13,644
203,998
kWh
$3,064
-
kW-mo/yr
$1,900
-
MMBtu
$(-300.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs