Assessment Year | 2011 |
---|---|
Principal Product | aircraft de-icing systems |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 370 |
Plant Area |
14,700
ft2
|
Annual Production | 115,000,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $125,492 | 4,899,679 |
kWh
|
$0.026 |
Electricity Demand | $137,023 | 12,419 |
kW-mo/yr
|
$11.03 |
Natural Gas | $331,669 | 27,472 |
MMBtu
|
$12.07 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $35,318 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,833 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $19,052 | $63,760 |
$(-19.0)
(-756)
kWh
|
$(-132.0)
-
kW-mo/yr
|
$19,203
-
MMBtu
|
|
02 | 2.2414: Use waste heat from hot flue gases to preheat | $6,433 | $8,495 | - | - |
$6,433
-
MMBtu
|
|
03 | 2.4239: Eliminate or reduce compressed air usage | $4,569 | $14,510 |
$2,876
111,398
kWh
|
$1,693
-
kW-mo/yr
|
- | |
04 | 2.2437: Recover waste heat from equipment | $4,500 | $4,500 | - | - |
$4,500
-
MMBtu
|
|
05 | 2.4221: Install compressor air intakes in coolest locations | $764 | $480 |
$411
15,991
kWh
|
$353
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $35,318 | $91,745 |
$3,268
126,633
kWh
|
$1,914
-
kW-mo/yr
|
$30,136
-
MMBtu
|
||
TOTAL IMPLEMENTED | $9,833 | $19,490 |
$3,287
127,389
kWh
|
$2,046
-
kW-mo/yr
|
$4,500
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs