Assessment Year | 2010 |
---|---|
Principal Product | Printed Circuit Board |
NAICS | 334412: Bare Printed Circuit Board Manufacturing |
SIC | 3672: Printed Circuit Boards |
Sales Range | $10 M to 50M |
# of Employees | 104 |
Plant Area |
65,000
ft2
|
Annual Production | 1,000,000
pieces
|
Production Hrs. Annual | 4,590
hrs
|
Location (State) | Maryland |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $275,922 | 2,656,830 |
kWh
|
$0.10 |
Electricity Demand | $13,274 | 5,451 |
kW-mo/yr
|
$2.44 |
Natural Gas | $15,912 | 1,469 |
MMBtu
|
$10.83 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $110,734 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $100,875 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $92,924 | - | - | - | $92,924 | - | - | |
02 | 2.7229: Air condition only space necessary | $6,499 | $900 |
$4,232
40,727
kWh
|
$144
-
kW-mo/yr
|
- |
$2,123
-
MMBtu
|
- | |
03 | 2.7224: Reduce space conditioning during non-working hours | $3,551 | $2,200 |
$1,721
16,572
kWh
|
- | - |
$1,830
-
MMBtu
|
- | |
04 | 2.4312: Improve lubrication practices | $1,907 | $618 |
$1,850
17,806
kWh
|
$57
-
kW-mo/yr
|
- | - | - | |
05 | 2.7231: Use radiant heater for spot heating | $1,430 | $5,800 | - | - | - |
$1,430
-
MMBtu
|
- | |
06 | 2.7135: Install occupancy sensors | $1,273 | $210 |
$1,200
11,545
kWh
|
$73
-
kW-mo/yr
|
- | - | - | |
07 | 2.7313: Recycle air for heating, ventilation and air conditioning | $1,222 | $3,100 | - | - | - |
$1,722
-
MMBtu
|
$(-500.0) | |
08 | 2.7111: Reduce illumination to minimum necessary levels | $1,020 | $67 |
$961
9,253
kWh
|
$59
-
kW-mo/yr
|
- | - | - | |
09 | 2.2437: Recover waste heat from equipment | $563 | $274 | - | - | - |
$563
-
MMBtu
|
- | |
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $200 | $20 |
$188
1,727
kWh
|
$12
-
kW-mo/yr
|
- | - | - | |
11 | 2.4221: Install compressor air intakes in coolest locations | $145 | $440 |
$138
1,333
kWh
|
$7
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $110,734 | $13,629 |
$10,290
98,963
kWh
|
$352
-
kW-mo/yr
|
$92,924 |
$7,668
-
MMBtu
|
$(-500.0) | ||
TOTAL IMPLEMENTED | $100,875 | $3,115 |
$5,920
56,903
kWh
|
$201
-
kW-mo/yr
|
$92,924 |
$1,830
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs