Assessment Year | 2010 |
---|---|
Principal Product | Core Veneer |
NAICS | 321211: Hardwood Veneer and Plywood Manufacturing |
SIC | 2435: Hardwood Veneer and Plywood |
Sales Range | $10 M to 50M |
# of Employees | 221 |
Plant Area |
190,375
ft2
|
Annual Production | 175,000,000
units
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | West Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $624,450 | 23,065,269 |
kWh
|
$0.027 |
Electricity Demand | $563,339 | 41,983 |
kW-mo/yr
|
$13.42 |
Electricity Fees | $1,084 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $554,774 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $179,296 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3414: Burn waste to produce steam to drive a steam turbine generator set and use steam exhaust for heat | $215,411 | $540,000 |
$140,315
5,027,400
kWh
|
$96,311
-
kW-mo/yr
|
$(-21,215.0)
-
MMBtu
|
- | |
02 | 2.2437: Recover waste heat from equipment | $154,014 | $106,000 | - | - |
$154,014
-
MMBtu
|
- | |
03 | 2.2514: Cover open tanks | $83,144 | $7,290 | - | - |
$83,144
-
MMBtu
|
- | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $37,930 | $39,900 | - | - |
$37,930
-
MMBtu
|
- | |
05 | 2.4151: Develop a repair/replace policy | $18,121 | $1,644 |
$10,834
388,177
kWh
|
$7,443
-
kW-mo/yr
|
- | $(-156.0) | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $16,812 | - |
$9,973
357,321
kWh
|
$6,839
-
kW-mo/yr
|
- | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,889 | - |
$5,878
210,682
kWh
|
$4,011
-
kW-mo/yr
|
- | - | |
08 | 2.4239: Eliminate or reduce compressed air usage | $6,515 | $1,717 |
$3,860
138,294
kWh
|
$2,655
-
kW-mo/yr
|
- | - | |
09 | 2.4157: Establish a predictive maintenance program | $3,930 | $1,000 |
$3,378
121,016
kWh
|
$2,320
-
kW-mo/yr
|
- | $(-1,768.0) | |
10 | 2.2511: Insulate bare equipment | $2,955 | $3,544 | - | - |
$2,955
-
MMBtu
|
- | |
11 | 2.2437: Recover waste heat from equipment | $2,309 | $4,560 | - | - |
$2,309
-
MMBtu
|
- | |
12 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,246 | $26 |
$1,334
47,785
kWh
|
$912
-
kW-mo/yr
|
- | - | |
13 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,498 | $4,153 |
$667
23,906
kWh
|
$831
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $554,774 | $709,834 |
$176,239
6,314,581
kWh
|
$121,322
-
kW-mo/yr
|
$259,137
-
MMBtu
|
$(-1,924.0) | ||
TOTAL IMPLEMENTED | $179,296 | $55,095 |
$33,923
1,215,490
kWh
|
$23,268
-
kW-mo/yr
|
$124,029
-
MMBtu
|
$(-1,924.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs