ITAC Assessment: WV0340
ITAC logo
ITAC Assessment: WV0340
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product olefin foams polypropylene and polyethylene
NAICS 326113: Unlaminated Plastics Film and Sheet (except Packaging) Manufacturing
SIC 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 128,000
ft2
Annual Production 3,264
ton
Production Hrs. Annual 8,568
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $433,048 16,503,374
kWh
Electricity Demand $216,006 28,883
kW-mo/yr
Electricity Fees $28,883 -
Natural Gas $1,232,952 134,217
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $164,193 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $145,210

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.2113: Repair or replace steam traps $80,134 $2,500 - - $81,754
-
MMBtu
$(-1,620.0)
02 2.2442: Preheat combustion air with waste heat $42,375 $27,500 - - $42,375
-
MMBtu
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $10,539 $29,343 $7,659
273,592
kWh
$2,880
-
kW-mo/yr
- -
04 2.2511: Insulate bare equipment $8,729 $2,605 $999
35,702
kWh
$376
-
kW-mo/yr
$7,354
-
MMBtu
-
05 2.2437: Recover waste heat from equipment $4,797 $1,520 - - $4,797
-
MMBtu
-
06 2.2628: Utilize a less expensive cooling method $3,647 $6,520 $2,624
93,760
kWh
$1,023
-
kW-mo/yr
- -
07 2.4314: Use synthetic lubricant $3,001 $90 $2,181
77,938
kWh
$820
-
kW-mo/yr
- -
08 2.4157: Establish a predictive maintenance program $2,647 $1,000 $2,348
83,798
kWh
$884
-
kW-mo/yr
- $(-585.0)
09 2.4221: Install compressor air intakes in coolest locations $2,384 $800 $1,730
61,821
kWh
$654
-
kW-mo/yr
- -
10 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,262 - $1,645
58,893
kWh
$617
-
kW-mo/yr
- -
11 2.4151: Develop a repair/replace policy $2,152 $439 $2,348
83,798
kWh
$884
-
kW-mo/yr
- $(-1,080.0)
12 2.4231: Reduce the pressure of compressed air to the minimum required $928 $1,270 $672
24,108
kWh
$256
-
kW-mo/yr
- -
13 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $598 $1,170 $500
17,897
kWh
$188
-
kW-mo/yr
- $(-90.0)
TOTAL RECOMMENDED $164,193 $74,757 $22,706
811,307
kWh
$8,582
-
kW-mo/yr
$136,280
-
MMBtu
$(-3,375.0)
TOTAL IMPLEMENTED $145,210 $37,374 $12,423
443,955
kWh
$4,679
-
kW-mo/yr
$131,483
-
MMBtu
$(-3,375.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs